Your Directors are pleased to present the22ndAnnual Report and Audited FinancialStatements for the Financial Year ended 31 March,2025 together with the reports of StatutoryAuditors.Comments of Comptroller & AuditorGeneral of India are yet to be received by theCompany.
1. Financial Performance Highlights
The key highlights of the financialperformance of the company during FY2024-25 along with the correspondingperformance in F.Y. 2023-24 are mentionedbelow (rounded to nearest rupees/crore):
Particulars
2024-2025
2023-24
1
%
Increase/
Decrease
Turnover
19,869.35
21,732.58
-8.57%
Total Income
20,888.24
22,915.13
-8.85%
Operating Income
1,484.15
1,691.34
-12.25%
Reserves & Surplus
6,538.70
5,782.26
13.08%
Profit Before Tax
1,550.17
1,939.40
-20.07%
Profit After Tax
1,188.62
1,462.95
-18.75%
Net worth
8,623.72
7867.28
9.62%
Appropriations
Dividend
*358.62
439.94
-18.48%
* Final dividend amounting to Rs 358.62 crore @ Rs 1.72 per fully
paid equity share recommended by the Board of Directors subjectto the approval of shareholders in the ensuing Annual GeneralMeeting of the Company.
Capital Structure
With an Authorized share capital of theCompany of Rs. 3000 crores, there has beenno change in the Capital Structure of theCompany, with the Paid-up share capital ofthe Company remaining at Rs. 2085.02 crore.The Company has not issued any share duringthe year under consideration.
Your Company has not provided anyEmployee Stock Option Plan (ESOP);therefore, disclosure requirement in relationto ESOP under Rule 12(9) and Rule 16(4) ofthe Companies (Share Capital andDebentures) Rules, 2014 is not applicable.
As on 31.03.2025, the present Shareholding ofPresident of India (POI) is 1,51,87,43,694 equityshares of Rs. 10 each amounting to Rs.15,18,74,36,940 that is 72.84%.
Profit
Profit before Tax decreased from Rs. 1,939.40crore in 2023-24 to Rs. 1,550.17 crore in 2024¬25 showing an decrease of 20.07%. Profit afterTax decreased from Rs. 1,462.95 crore in FY
2023- 24 to Rs. 1,188.62 crore in FY 2024-25showing a decrease of 18.75%.
The Net Worth of your Company has increasedover the previous year from Rs.7,867.28 croreto Rs. 8,623.72 crore on account of transferof profits (after payment of Dividend& OCI).
Reserves
The Reserves & Surplus of the Company for FY
2024- 25 stand at Rs. 6538.70 crore ascompared to Rs. 5,782.26 crore in FY 2023-24,showing an increase of 13.08% from previousyear.
The Board recommended a final dividend ofRs. 358.62 crores (Rs. 1.72 per share) subjectto the approval of shareholders in the ensuingAnnual General Meeting of the Company.Total dividend for the financial year 2024-25is Rs. 358.62 crore.
Your company has not accepted any depositfrom the public during the year.
RVNL received an amount of Rs. 17,917.05crore (approx.) for project expenditure duringthe current year, from Ministry of Railways(MoR) for execution of various works.
During the year, no borrowing was madefrom IRFC. With this, the total amountreceived from IRFC is Rs. 7865.08 crore. Theprincipal and interest on the borrowings fromIRFC are repaid by Ministry of Railways (MoR)as a pass-through entry in the books of RVNL.During the year, an amount of Rs.472.00crore
towards principal & Rs. 550.19 crore towardsinterest was paid to IRFC on this account,leaving an outstanding loan & Principalbalance of Rs. 5941.66 crore (includinginterest accrued of Rs.1449.30 Cr).
Your Company has achieved a turnover ofRs. 19,869.35 crore in 2024-25 as compared toRs. 21,732.58 crore in 2023-24.
In addition, over the years the Company hasalso put a large number of large valuecontracts in place to speed up the processof project execution. At the same time, therehas also been a significant increase in therevenue from the projects secured throughbidding to the tune of Rs. 2771.50 crore during2024-25 in comparison to Rs. 1698.78 crore inthe previous year.
The consolidated Financial Statements of theCompany prepared in accordance with theprovisions of Companies Act, 2013 and theapplicable Indian Accounting Standards(IND-AS) for the financial year 2024-25 formspart of the Annual Report of the Company.The accounts have been consolidated basedon the performance and activities of theSPVs, JVs, Associates and the share of RVNLin those entities as an equity partner and itswholly owned subsidiaries. The related entriesappearing in the standalone accounts ofRVNL have been adjusted accordingly inconsonance with the relevant IndianAccounting Standards (Ind AS 110 & 28). Thesalient features of differences in the significantentries between the Standalone Accounts ofRVNL and the Consolidated Accounts are asunder:
Particular
Figures as
on 31.03.2025
Standalone
Consolidated
19869.35
19923.02
Other Income
1018.89
999.78
Direct Expenses
18385.20
18406.31
Indirect Expenses
952.87
961.87
PBT
1550.17
1554.62
PAT
1188.62
1281.52
Reserve & Surplus
6538.70
7485.99
Net Worth
8623.72
9571.01
** PBT includes Rs. 95.41crore as proportionate shareof RVNL in the profit/loss of Joint Ventures.
A report on the performance and financialposition of subsidiary, associates and jointventure Company as per Companies Act,2013 is provided in Note-43 to theConsolidated Financial Statements.
2. Integral Reports
The Management Discussion and Analysis
Report provides an overview of the affairs ofthe Company, its business environment,mission and objectives, outlook, operationalperformance, its resources and systems,strengths, opportunities, constraints, risks andconcerns, strategies, prospects, etc.(Annexure A).
The Corporate Governance Report highlightsthe Company's philosophy on CorporateGovernance and Key Values, composition ofBoard of Directors and its Committees,attendance and remuneration of Directorsetc. other relevant disclosures, CEO/CFOCertification and general information forshareholders. The following compliancecertificates as required under DPE Guidelinesand SEBI Regulations supplement it.(Annexure B).
A Certificate signed by the Chairman andManaging Director affirming receipt ofcompliance with the Code of Conductfrom all Board members and SeniorManagement personnel during the year2024-25(placed at Annexure “B-1”) as perguidelines of Department of PublicEnterprises on Corporate Governance.
A Certificate from the Chairman andManaging Director (CMD) and ChiefFinancial Officer (CFO) with regard tothe authenticity of financial statements(placed at Annexure “B-2”); and
A Certificate of compliance on Corporate
Name of Report
Annexure
Management Discussion andAnalysis
A
Corporate Governance Report
B
Corporate Social Responsibility(CSR) Report
C
"Business Responsibility andSustainability Report (BRSR)"
D
Secretarial Auditor Report
E
Form AOC-2
F
Governance signed by a practicingCompany Secretary (placed at Annexure“B-3”) as per guidelines of Department ofPublic Enterprises on CorporateGovernance and Listing Regulations.
Certificate on non-disqualification ofDirectors as per schedule V of SEBI(LODR) Regulations, 2015 (placed atAnnexure “B-4”)
The Corporate Social Responsibility (CSR)Report reflects RVNL's plans, policy, budget,expenditure, evaluation process for projectsand CSR activities undertaken during theyear. (Annexure C)
The “Business Responsibility andSustainability Report (BRSR)”describes the
initiatives taken by the Company from anEnvironmental, Social and Governance (ESG)perspective in terms of amendment toRegulation 34 (2) (f) of SEBI (LODR)Regulations 2015.(Annexure D)
Pursuant to provisions of Section 204 ofCompanies Act, 2013 and Companies(Appointment and Remuneration ofManagerial personnel) Rules 2014, theCompany has appointed M/s. Kumar NareshSinha & Associates, Practicing CompanySecretary, to undertake the Secretarial Auditof the Company. The Secretarial Audit Reportis placed at Annexure “E”.
As per Section 92 (3) of the Companies Act,2013, Annual Return will be available on thewebsite of the Company i.e., www.rvnl.org.
The disclosure of Related Party Transactions,as required under section 134 (3) (h) ofCompanies Act, 2013 and Rule 8 (2) of theCompanies (Accounts) Rules, 2014 in Form“AOC-2” is placed at Annexure “F”.
Your Directors are delighted to inform thatthe F.Y. 2024-25 has been a year of excellenceand growth for the Company.
In 2024-25, 345.89 km sections werecommissioned consisting of 3.2 km of NewLine and 342.69 km of Doubling handed overto Zonal Railways for operations.
During the year, 5 important projects werefully commissioned. These are:
Rajpura- Bhatinda (172.64 km) DoublingJanghai- Phahamau Doubling
Varanasi- Madhosingh- AllahabadDoubling
Daraganj- Rebuiding (Bridge No. 111 onGanga)
Pamban Bridge (Lifting Span Bridge)
The year 2024-25 was significant in Indianhistory for organizing largest gathering atPrayagraj during Maha Kumbh. The fastestcommissioning of Janghai- PhahamauDouble line Project (46.1 km), Varanasi-Madhosingh- Allahabad Double line Project(120.20 km) and Daraganj-Rebuilding (BridgeNo. 111 on Ganga, 1.934 km) has eased outrailway traffic during Maha Kumbh whichfacilitated Indian Railway to run 1000+ extratrains during this period.
The iconic Pamban Bridge of 2.1 km lengthcomprising of India's first vertical lifting spanover Bridge of 72-meter span was completedin November 2024 that connected the townof Rameswaram on Pamban Island withMandapam in mainland. World's mostadvanced technologies have been used inconstruction of Pamban Bridge. The Bridgewas inaugurated by the Shri Narendra ModiHonourable Prime Minister of India. Nearly 14passenger trains run daily over this newconstructed bridge which carries thousandsof passengers to Rameswaram.
During the year, with the focus of the Ministryon the commissioning of RailwayElectrification projects, Companycommissioned 158.19 km of RailwayElectrification. In addition, RailwayElectrification of 324.83 km was also carriedout in other than specific RailwayElectrification projects as part of Doubling.Thus, 483.02 km of electrified sections werecommissioned in 2024-25.
Since its establishment in 2003, Ministry ofRailways has transferred 185 projects to RVNLfor execution, which may be broadlyclassified under the following heads:
• Doubling 70
• Gauge Conversion 12
• New Lines 12
• MTP 06
• Railway Electrification 39
• Workshops 21
• Others 25
And after implementation of revocation ofpolicy for assignment of work to PSUs in 2021,RVNL had participated in Open Bidding andprojects awarded through biddings as onMarch 2025 are:
• Awarded through Bidding 94
The distribution of project length undervarious plan heads is shown below:
Deatils of Projects
16000
__¦ Completed upto
14000
March 2025
12000
7768
1rtnnn 693410000
8000 ^
445
—
25
6000 1256
4000 (
5489
7743
1C. 46
2000 633.
155
7
r a
0
J>z
& ^
oh 39& X?
cr
* Figure indicates Number of Projects
The list of 157 projects fully completed ud to March 2025 is as under:
S.
No.
Railway
Project Name
Type ofProject
Length
(km)
1.
Central Railway
Diva - Kalyan 5th & 6th Line
Doubling
11
2.
Pakni - Mohol Doubling
17
3.
Panvel - Jasai JNPT Doubling
28.5
4.
Pakni - Solapur Doubling
16.28
5.
Central Railway& SCR
Daund- Gulbarga- Doubling (224.9 km) andPune- Guntakal -Electrification (641.37 km)
224.9
6.
Eastern Railway
Gurup - Saktigarh Extn of 3rd Line
26
7.
East Central Railway
Barauni - Tilrath Bypass Doubling
8.3
8.
East Coast Railway
Talcher-Cuttack-Paradeep Doubling with 2ndBridge on Rivers Birupa & Mahanadi
3
9.
Jakhapura- Haridaspur 3rd Line
23.3
10.
Cuttack - Barang Doubling
14.3
11.
Rajatgarh-Barang Doubling
31.3
12.
Khurda-Barang - 3rd line (35 km)
32.32
13.
Sambalpur-Titlagarh (182 km)
182.00
14.
Raipur-Titlagarh (203 km)
203
15.
Banspani-Daitari-Tomka-Jakhapura (180 km)
180
16.
Northern Railway
New Delhi-Tilak Bridge- 5th & 6th line (2.65 km)
2.65
17.
Utraitia-Raebareli (65.6 km)
68.04
18.
Raebareli-Amethi (60.1 km)
59.00
19.
Raipura-Bhatinda Doubling with Electrification(172.64 km)
172.64
20.
North Central Railway
Palwal - Bhuteswar 3rd Line
81
21.
Aligarh - Ghaziabad 3rd Line
106.1
22.
Bhimsen-Jhansi (206 km) with RE
206
23.
North Western Railway
Bhagat Ki Kothi - Luni Doubling
30.3
24.
Karioda - Palanpur Doubling
5.4
25.
Rewari- Manheru Doubling
69.02
26.
Rani-Keshav Gani Doubling
59.5
27.
Abu Road-Sarotra Road- Patch doubling (23.12 km)
23.12
28.
Swaruganj-Abu Road - Patch doubling (25.36 km)
25.36
29.
Sarotra Road-Karjoda - Patch doubling (23.59 km)
23.59
30.
Southern Railway
Attipattu - Korukkupet 3rd Line
18
31.
Pattabiram - Tiruvallur 4th Line & Tiruvallur -Arakkonam 3rd Line
41.89
32.
Tiruvallur - Arakkonam 4th Line
28
33.
Villipuram-Dindigul Doubling
273
34.
Thanjavur-Ponmalai - Doubling
46.96
35.
Madurai-Maniyachi-Tuticorin (160 km)
160
36.
Maniyachi-Nagercoil DL
102
37.
South Central Railway
Pullampet - Balapalle Ph I of Gooty - ReniguntaDoubling
41
38.
Krishnapatnam - Venkatachalam Doublingwith RE
16.5
39.
Gooty - Renigunta Patch Doubling
151
40.
Raichur - Guntakal Doubling
81.0
41.
Guntur-Tenali - Doubling with electrification(24.38 km)
42.
Vijaywada-Gudivada-Bhimavaram-Narasapur, Gudivada-Machlipatnam andBhimavaram-Nidadavolu (221 km) - Doublingwith electrification
221.00
43.
Secunderabad (Falaknuma)-Mehbubnagardoubling
85.70
44.
South Eastern Railway
Tikiapara - Santragachi Doubling
5.6
45.
Panskura - Kharagpur 3rd Line
45
46.
Panskura - Haldia Ph 1 Doubling
14
47.
Rajgoda - Tamluk (Jn. Cabin) Doubling
13.5
48.
Tamluk Jn. Cabin - Basulya Sutahata Doubling
24.23
49.
Goelkera-Monoharpur 3rd line (40 km)
27.5
50.
South East Central Railway
Bilaspur - Urkura 3rd Line Doubling
105
51.
Salka Road- Khongsara Patch Doubling
52.
Khodri-Anuppur, with Flyover at Bilaspur (61.6 km)
61.6
53.
South Western Railway
Hospet - Guntakal Doubling
115
54.
West Central Railway
Bhopal-Bina - 3rd line (143 km)
144.3
55.
Itarsi-Budni - 3rd line (25.090 km)
25.09
56.
Barkhera-Habibganj - 3rd line (41.420 km)
41.2
57.
Bina-Kota (282.66 km) with RE
282.66
58.
Barkhera - Budni 3rd line
26.5
59.
Western Railway
Palanpur- Samakhiali (247.73 km)
247.3
60.
North Eastern Railway
Lucknow-Pilibhit via Sitapur, Lakhimpur (262.76 km)
GC
262.76
61.
Delhi - Rewari Gauge Conversion
94.2
62.
Ajmer - Phulera - Ringus - Rewari Gauge Conversion
295
63.
Bhildi - Samdari Gauge Conversion
223
64.
Thanjavur - Villupuram Gauge Conversion
192
65.
Cuddalore - Salem Gauge Conversion
193
66.
Arasikere-Hassan-Mangalore Gauge Conversion
230
67.
Bharuch - Samni - Dahej Gauge Conversion
62
68.
Gandhidham - Palanpur Gauge Conversion
301
69.
Ahmedabad-Botad (170.48 km)
166.09
70.
Dhasa-Jetalsar (104.44 km)
106.69
71.
Daitari - Banspani New Line
New Line
72.
Haridaspur-Paradeep (82 km)
82
73.
Angul- Sukinda Road (98.7 km)
95
74.
Mau-Gazipur-Tarighat New Line
16.79
75.
Vallarpadam - Idapally New Line
9
76.
Obulavaripalle- Krishnapattnam (113 km)
121
77.
Railway Electrification
Tomka -Banspani - RE
RE
144
78.
Kharagpur (Nimpura) - Bhubaneswar IncludingBranch Line of Talcher - Cuttack - Paradeep
581
79.
Bhubaneswar - Kottavalasa
417
80.
Daund-Manmad Incl. Puntamba- Shirdi - RE
255
81.
Reningunta - Guntakal RE
308
82.
Yelahanka - Dharmavaram - Gooty RE
306
83.
Bharuch - Samni - Dahej RE
64
84.
Manheru- Hissar RE
74
85.
Jakhal - Hisar (79 km)
80.0
86.
Chhapra-Ballia-Ghazipur-Varanasi-AllahabadRE (330 km)
330
87.
Guntakal-Kalluru RE (40 km)
40
88.
Utretia - Rae Bareli - Amethi - Janghai RE (214 km)
214
89.
Daund-Baramati (44 km)
44
90.
Amla-Chhindwara-Kalumna
257
91.
Raipur-Titlagarh (203 km) {Part of Vizianagaram -Rayagada - Titlagarh - Raipur (465 km)}
92.
Rajpura - Dhuri - Lehra Mohabat (151 km)
93.
Guntakal - Bellary - Hospet incl. Tornagallu -
138
Ranjitpura Branch Line (138 km)
94.
Wani- Pimpalkutti RE (66 km)
66
95.
Manoharabad- Medchal (14 km)
96.
Yalahanka-Penukonda (120.55 km)-Doubling
-
97.
Jakhal - Dhuri - Ludhiana (123 km)
123
98.
Guna-Gwalior (227 km)
227
99.
Rani-Palanpur 166 km
166
100.
Villupuram-Cuddalore Port-Mayiladuturai-Thanjavur& Mayiladuturai-Thiruvarur (228 km)
228
101.
Raebareli-Unchahar incl. Dalmau-Daryapur (63 km)
63
102.
Raninagar Jalpaigudi-New Bongaigaon -Guwahati (Incl) RE (382 km) (Part of Barauni -Katihar - Guwahati Incl. Katihar - Barsoi (836 km) RE
374.98
103.
Chikjajur-Bellary RE (184 km)
183.15
104.
Bengaluru-Omalur Via Hosur RE (196 km)
196.00
105.
Utratia-Raebareli-Amethi 2nd line RE (126 km)
126.00
106.
RE of Sambalpur-Titlagarh Doubling project (96.596 km)
96.60
107.
Palanpur-Samakhiali (247.73 km) RE
247.73
108.
Kasganj-Bareilly-Bhojipura-Daliganj RE (401 km)
401
109.
RE of Dhasa - Jetalsar (104.44 km)
104.44
110.
Deposit
RE of NTPC siding at Hotgi Station (37 km)
34.41
111.
Electrification of IOCL Siding at Pakni (4 km)
4.15
112.
Electrification of Ultra Tech Cement Siding atHotgi (8km)
9.75
113.
Electrification of Chettinad Cement Siding atTilati (7.1km)
5.9
114.
Latur- Setting up of coach manufacturing factory
WKSP
115.
Civil Engineering Works in Connection with DieselLoco Component Factory, Dankuni
116.
Dankuni - Setting Up of Electric Loco Assembly andAncillary Unit of CLW
117.
Ranaghat (EMU Car Shed)-Inspection bay for 15coach maintenance facilities
118.
Jheel Siding Coaching Depot- Infrastructuredevelopment
119.
Barauni - 250 High Horse Power Loco Shed
120.
Gaya -Setting up New MEMU car shed formaintaining 30 rakes of 16 coaches
121.
Vadlapudi- Wagon PoH Workshop of 200 NosCapacity Near Duvvada Station
122.
Khurda Road - Construction of main line electricalmultiple unit car shed (Phase-2)
123.
Kanpur - Construction of MEMU Car shed
124.
Jhansi-Setting up of coach periodic overhaulingand refurbishment workshop
125.
Saidpur Bhitri- Setting up of Electric Loco Shed tohome 200 Locos
126.
Dullahapur Yard - Provision of tower wagonperiodic overhauling shed
127.
Sonipat-Setting up of coach periodical overhaulingand refurbishment workshop
128.
Setting Up of Diesel Multiple Unit (DMU)Manufacturing Factory at Sankrail/ Haldia
129.
DLW
Varanasi - Augmentation of Production Capacityfrom 200 To 250 High HP Locos Per Year
130.
Aunrihar - DEMU Shed
131.
Workshop for Manufacture of Flat Bogies for LHBDesign Coaches, Yadgir
132.
Vadodara - Setting up of New PoH Shop for
Electrical Locos
133.
Hyderabad-Secunderabad - Multi modal transportsystem (Phase-II)-MTP
MTP
78
134.
METKOL
MM of Existing Corridor Noparanagar-Baranagar-Daksineshwar
4.14
135.
Barddhaman Yard - 4-lane road over bridge inlieu of 2-lane road over bridge No. 213
ROB
136.
Srirangam-Tiruchchirapalli Town - 4-lane roadover bridge in lieu of 2- lane bridge No.380-A
137.
IOC Siding at Salawas (Deposit Work)
Others
2.82
138.
Secunderabad- Upgradation of facilities atCentralised Training Academy for Railway Accounts
TRG
139.
Moula Ali - Setting Up of Indian Railway Institute ofFinance Management
140.
Lallaguda (Carriage Workshop)- Replacement of100-Year-Old Administrative Building
OSW
141.
New Station Building at Belguam
142.
Second Entry Station Building at Belguam
143.
Proposed Coaching Depot at Belgaum
144.
Yard Remodelling Works at Belgaum
145.
Madar - Palanpur - Removing of PSR (Kms 589/1to 590/1)
Track
Renewal
146.
Jhansi-Garhmau, Orai-Ata, Ata-Kalpi &Pokhrayan-Lalpur - Splitting of longer block sections
TF
147.
Paman-Bhimsen - New B-class station
148.
Umdanagar-Timmapur - New crossing station
TFC
149.
Sabarmati-Botad-subways in lieu of levelcrossing-23 Nos.
RSW
150.
Sabarmati-Botad-Subways in lieu of LCs-14 Nos.
151.
Dhasa-Jetalsar-Subways in lieu of LevelCrossing-35 Nos.
152.
Final Location Survey for New Line Connectivity toChar Dham (327 km)
FLS
Following projects completed in 2024-25:
153.
Janghai- Phahamau DL
49.16
154.
Varanasi- Madhosingh- Allahabad
120.35
155.
Daraganj- Rebuiding (Bridge No. 111 on Ganga)
BRWG
1.934
156.
3.959
157.
RE of Ahmedabad- Botad (170.48 km)
170.48
RVNL is executing all types of RailwayInfrastructure works such as New Line, GaugeConversion, Doubling/3rd Line/4th Line,Railway Electrification, Workshops, HillRailway Projects, Institutional Buildings, MegaBridges, Metro Railway, Tunnels, MonumentalBridges, Canals, Transmission Lines, Highways,Signaling Work, MMLPs etc.
These projects are spread all over the countryand for efficient implementation of projects,29 Project Implementation Units (PIUs)established at 25 locations to executeprojects in their geographical hinterland. Theyare located at Ahmedabad, Bengaluru,Bhopal, Bhubaneshwar, Chennai (2 Units),Chandigarh, Gwalior, Indore, Kanpur,Kolkata (3 Units), Kharagpur, Kota, Lucknow,Mumbai, Nagpur, Patna, Pune, Raipur,Rishikesh, Ranchi, Secunderabad, Varanasi (2Units) and Waltair. Two projects units are also
established outside India, one is at Maldives& another is at Rwanda. The PIUs areestablished and closed as per requirement.
The status of the 279 projects assigned to RVNLfor execution is as under: -
Projects completed up to March 2025 :157 No.
61 No.
Gauge Conversion
11 No.
New Lines
06 No.
02 No.
38 No.
Workshops
19 No.
20 No.
Projects under implementation :
120 No.
MoR :
28 No
Bidding Works :
94 No.
Cumulatively, RVNL has completed a totalof 6489.06 km of doubling, 2120.36 km of
gauge conversion, 623.49 km of new lines,7743.30 km of pure Railway Electrification,4479.96 km RE as part of NL/Gc/DL and 84.40km of Metropolitan Transport Project (MTP).Thus, as on 31.3.2025, 17060.61 km of projectlength of 185 sanctioned projects assignedto RVNL, have been completed.
During 2024-25, 310.36 km (8.3 km of New Line,302.06 of Doubling and 2 Bridge Works Projecthave been physically completed. 159 km ofRailway Electrification was carried out duringthe year and in addition, RailwayElectrification of 298.11 km was also carriedout in other than specific RailwayElectrification projects as part of Doubling.
Head: During the year, 8.3 km of New Linewas completed, the details are givenbelow:
3.4.1.1 Bhanupalli - Bilaspur - Beri (63.1 km) :Duringthe year, Shri Anandpur Sahib- Nangal Dam(3.2 km) section was completed in February2025.
3.4.1.2 Neora - Daniawan (40.92 km): During theyear, Sarasa Jamalpur - Barbigha (5.1 km)section was completed in February 2025.
3.4.2 Sections completed under Doubling PlanHead: During the year, 302.06 km ofDoubling was completed, the details aregiven below:
3.4.2.1 Dhanbad - Sonnagar (Patratu - Sonnagar)
- 3rd Line (291 km): During the year, 49.44km of project length was completed.Mangra - Barwadih (5.82 km) wascompleted in April 2024, Untari Rd. -Karkatta (4.2 km) was completed in May2024, Barwadih - Chhipadohar (9.76 km)was completed in August 2024, Satbahini -Untari Rd. (4.93 Km) completed in August2024, Richughuta - Chetar (8.33 km) wascompleted in September 2024,Muhammadganj - Satbahini (6.84 km) wascompleted in December 2024 and Chetar
- Tori (TORI) (9.56 km) was completed inMarch 2025.
Line (264.60 km): During the year, 62.205 kmof project length was completed.
Narsipuram (NSX) - Parvatipuram (PVP) (4.42km) and Sitanagaram (SNM) - Narsipuram(NSX) 8.385 km were completed in May2024, Bobbili (VBL) - Narsipuram (NSX) (11.273km) was completed in July 2024,Donkinavalasa (DNV) - Bobbili (VBL) 11.958km was completed in August 2024,Bissamcuttack - Muniguda 16.97 km wascompleted in September 2024 and SingpurRoad Jn. (SPRD) - Theruvali Jn. (THV) (9.195km) was completed in December 2024.
3.4.2.3 Hospet - Hubli - Tinaighat (352 km): Duringthe year, 13.83 km of project length wascompleted, Tinaighat - Duski (9.46 km) andMajodara Jn.-Cansulim (4.37 km) werecompleted in April 2024.
3.4.2.4 Phephna- Indara, Mau - Shahganj (excl.Indara - Mau) (150.28 km) DL: During theyear, 19.80 km of project length wascompleted. Phariha - Sanjarpur (5.00 km)was completed in August 2024, Sanjarpur -Saraimir (5.9 km) was completed in October2024 and Saraimir - Khorasan Road (KRND)(8.9 km) was completed in December2024.
3.4.2.5 Bhatni- Aunrihar (126.30 km): During theyear, 33.36 km of project length wascompleted. Hurmujpur - Sadat (SDT) (6.11km), Dullahpur - Jakhanian (8.45 km) andJakhanian - Hurmujpur (3.7 km) werecompleted in September 2024. Pipradih -Nayakdeeh (4.98 km) and Nayakdeeh-Dullahpur (5.08 km) were completed inJanuary 2025 and Peokol - Salempur (5.04km ) was completed on February 2025.
3.4.2.6 Janghai-Phaphamau DL with Electrification(46.79 Km): During this year, 46.16 km projectlength was completed. Janghai Jn. -Baryaram (5.07 km) was completed on April2024, Baryaram - Ugrasenpur (9.00 km ) wascompleted on June 2024, Ugrasenpur -Phulpur (8.555 km ), Phulpur - Saraichandi(11.38 km) and Saraichandi - Tharwai (6.66km) was completed in December 2024 withthis completing the project fully.
3.4.2.7 Vijayawada - Gudur 3rd Line (287.67 km):During the year, 55.69 km of project lengthwas completed. Krishna Canal Jn. (KCC) -Kolanukonda (KAQ) (H)- Peddavadlapudi(PVD) (7.1 km),Peddavadlapudi (PVD) -Chiluvur (CLVR) (3.82 km) and Tenali -Tsunduru (TSR) (11.18 km) were completedin June 2024. Chiluvur (CLVR) - Duggirala(DIG) (5.73 km) was completed in August2024 and Duggirala (DIG)- Kolakalur (KLX)
(H)- Tenali (10.06 km) was completed inOctober 2024.
3.4.2.8 Kharagpur - Adityapur 3rd line (132 km):During the year, Aditypur Yard (3.4 km) wascompleted in May 2024.
3.4.2.9 Varanasi - Madhosingh - Allahabad (120.20km): During the year, 7.33 km project lengthwas completed. Jhusi (JI)- Daraganj (DRGJ)(4.096 Km) and Daraganj (DRGJ) -Allahabad City (ALY) (3.234 km) werecompleted in December 2024 with thiscompleting the project fully.
3.4.2.10 Malkhedi- Mahadeo Khedi (MM of Mina -Kota Doubling): During the year, Malkhedi-Mahadeo Khedi (6.89 km) was completedin November 2024 with this completing theproject fully.
3.4.3 Sections completed under Pure RailwayElectrification Works: During the year, 159km of Railway Electrification wascompleted, the details are given below:
3.4.3.1 Hospet -Hubli-Vasco Da Gama: During theyear, Castle Rock- Carnozol (10 km) wascompleted in March 2025.
3.4.3.2 Dallirajhara-Rowghat During the year, 43km of project length was completed.Bhanupratappur - Antagrah (25 km) wascompleted in June 2024 and Antagarh-Taroki (18 km) was completed in December2024.
3.4.3.3 Sabarmati-Botad: During the year, 106 kmof project length was completed. Moriyay-Koth Gangad (52 km) was completed inJanuary 2025, Koth Gangad- Loliya (20 Km)was completed in February and Loliya-Bhimnath (34 km) was completed in March2025 with this completing the project fully.
3.4.4 Bridge Work projects completed: Duringthe year, 2 Bridge Work projects were fullycompleted, the details of which are asunder:
3.4.5 Daraganj- Rebuiding (Bridge No. 111 onGanga): The Daraganj- (Bridge No. 111 onGanga) was completed in November 2024along with completion of Varanasi-Madhosingh- Allahabad doubling project.
India's first vertical lifting span over Bridge(Total length 2.1 km) was completed inNovember 2024 combining innovation withthe rich legacy of the past, that connectedthe town of Rameswaram on PambanIsland with Mandapam in mainland.
Out of 157 projects completed so far, all the157 projects have been fully commissionedand handed over to Indian Railways foroperations and maintenance.
The list of 157 projects fully commissioned tillMarch 2025 is as under:
Central Railway & SCR
Daund- Gulbarga- Doubling (224.9 km)and Pune- Guntakal -Electrification (641.37 km)
Talcher-Cuttack-Paradeep Doublinjg with 2ndBridge on Rivers Birupa & Mahanadi
Rajatgarh-Barang - 3rd line
Khurda - Barang 3rd Line
Bhimsen- Jhansi (206 km) with RE
Rani-Keshav Ganj Doubling
Karjoda - Palanpur Doubling
Abu Road - Sarotra Road Patch Doubling
23.55
Abu Road - Swaroopganj Patch Doubling
New Delhi - Tilak Bridge 5th & 6th Line Doubling
Utretia-Rae Bareli (65.6 km)
Raebareli - Amethi (60.1 km)
Krishnapatnam - Venkatachalam DoublingWith RE
Secunderabad-Mehboobnagar (85.24 km)
South East Central Railway Bilaspur - Urkura 3rd Line Doubling
Khodri-Anuppur, with flyover at Bilaspur (61.6 km)
Budni - Itarsi 3rd Line
Barkhera- Habibganj - 3rd line (41.420 km)
143
Bina -Kota (282.66 km) with RE
Ahmedabad- Botad (170.48 km)
Dhasa- Jetalsar (104.44 km)
NL
Angul-Sukinda Road (98.7 km)
98.7
Obulavaripalle - Krishnapatnam New Line
Manheru- Hisar (74 km)
74.0
Chhapra-Ballia-Ghazipur-Varanasi-Allahabad (330 km)
Guntakal-Kalluru (40 km)
Daund- Bramati (44 km)
Titlagarh (Excl)-Raipur -RE
Utretia- Rae Bareli- Amethi- Janghai RE
Hospet - Guntakal And Tomagallu - Ranjitpura
Wani-Pimpalkutti (66 km)
Amla - Chhindwara - Kalumna (257 km)
Villupuram-Cuddalore Port-Mayiladuturai-Thanjavur & Mayiladuturai-Thiruvarur (228 km)
Raebareli-Unchahar incl. Dalmau-Daryapur (63 km
Raninagar Jalpaigudi-New Bongaigaon (incl.)-Guwahati (incl.)-382 rkm {Part of Barauni-Katihar-Guwahati incl Katihar-Barsoi (836 km)}
Chikjajur-Bellary (184 rkm)
Bengaluru-Omalur via Hosur (196 rkm)
2nd Line Utratia-Raebareli-Amethi (126 rkm)(Northern Railway) (PB#135/2018-19/CORE)
RE of Sambalpur-Titlagarh Doubling project (96.596 km.
Palanpur- Samakhiali (247.73 km) RE
Civil Engineering Works in Connection withDiesel Loco Component Factory, Dankuni
Dankuni - Setting Up of Electric Loco Assembly ancAncillary Unit of CLW
Vadlapudi - Wagon PoH Workshop of 200 Nos
Capacity Near Duvvada Station
Sonipat-Setting up of coach periodicaloverhauling and refurbishment workshop
Setting Up of Diesel Multiple Unit (DMU)Manufacturing Factory at Sankrail / Haldia
Varanasi - Augmentation of Production Capacityfrom 200 to 250 High HP Locos Per Year
Saidpur Bhitri- Setting up of electric loco shed tohome 200 locos
Vadodara - Setting up of New PoH Shop forElectrical Locos
Electrification of IOC Siding at Salawas(Deposit Work)
Madar - Palanpur - Removing of PSRKms 589/1 to 590/1)
TR
Moula Ali - Setting Up of Indian Railway Instituteof Finance Management
Lallaguda (Carriage Workshop)- Replacementof 100-Year-Old Administrative Building
Jhansi-Garhmau, Orai-Ata, Ata-Kalpi & Pokhrayan-Lalpur - Splitting of longer block sections
Umdanagar- Timmapur - New Crossing Station
Final Location Survey for New Line Connectivityto Char Dham (327 km)
The list of 6 projects fully commissioned in 2024-25 are as under:
Rajpura- Bhatinda (172.64 km)
173.38
In 2024-25, 345.89km sections were commissioned consisting of 3.2km of New Line and 342.69 km ofDoubling handed over to Zonal Railways for operations. 158.19 km of Railway Electrification was
also carried out, in addition, Railway Electrification of 324.83 km was also carried out in other thanspecific Railway Electrification projects as part of Doubling, the details are given below:
N.
Plan
Head
Name of work
Section Targeted
Section
Total
Zonal
Bhanupali- Bilaspur- Beri
Shri Anandpur Sahib - Nangal Dam
3.2
NR
Total New Line:
2
DL
Dhanbad-Sonnagar
Bendi (IBH) - Latehar - Demu -
20.55
46.85
ECR
(Patratu- Sonnagar) -
Richughuta
3rd line (291 km)
Japla (JPL) - Navinagar
15.83
Untari Rd. - Karkatta - Sigsigi
10.47
Vizianagaram-Sambhalpur (Titlagarh)
Doikallu (DKLU) - Ambodala (AMB) -Lajnjigarh Road Jn. (LJR)
25.39
55.54
ECOR
3rd line (264.60 km)
Doikallu - Muniguda - Bissamcuttack
30.15
4
Rajpura- Bhatinda(172.64 km)
Hadiaya (HYA) - Tapa (TPA) - RampuraPhul (PUL) - Lehra Muhabat (LHM)
33.47
5
Janghai- Phapamau DL Janghai Jn. - Baryaram - Ugrasenpur
17.07
Ugrasenpur - Phulpur - Saraichandi-
32.09
Tharwai - Phaphamau Jn.
6
Mathura- Jhansi-3rd
Hetampur - Dhaulpur
13.56
46.05
NCR
line (273.80 km)
Sandalpur - Antri
6.56
Gwalior - Sithouli - Sandalpur
16.04
Mathura - Baad
9.89
Varanasi-Madhosingh-
Allahabad City (ALY) - Allahabad
2.27
9.60
NER
Allahabad (120.20 km)
Jn. (ALD)
Jhusi (JI) - Daraganj (DRGJ) -Allahabad City (ALY)
7.33
8
Mau- Shahganj
Khorasan Rd - Didarganj - Shahganj
21.50
41.51
Phariha - Sanjarpur - Saraimir -Khorasan Road (KRND)
20.01
Bhatni- Aunrihar
Belthara Road - Govindpur Dugauli -Kidihrapur
13.85
32.36
Dullahpur - Jakhanian - Hurmujpur -Sadat (SDT)
18.51
10
Kharagpur- Adityapur3rd line (132 km)
Adityapur Yard
3.40
SER
Hospet- Tinaighat-
Majodara Jn.- Cansaulim
4.37
13.90
SWR
Vasco(362.73 Km)
Tinaighat- Duski
9.53
12
Bina- Kota DL
Malkhedi- Mahadeokhedi
6.89
WCR
13
BW
Pamban Bridge
3.96
SR
Total DL
342.69
G. Total
345.89
The list of Projects/ sections under Railway Electrifications plan head commissioned during 2024-25is as under:
Bnilwnv Electrification Projects
No
(Rkm)
Dallirajhara- Rowghat (95 km)
Dallirajhara-Bhanupratappur
25.90
43.04
SECR
Antagarh- Taroki
17.14
Sabarmati- Botad RE
Muraiya- Bhimnath
105.15
WR
Hospet- Hubli -Vasco Da Gama
Castle Rock-Carnanzol
10.00
RE Total (RKM):
158.19
The Signaling & Telecommunication (S&T) domain provides appropriate and cost-effective solutionsfor efficient and safe operation of trains on Indian Railways. RVNL promotes use of moderntechnologies on Indian Railways namely Electronic Interlocking (EI), Digital Axle Counters, FiberOptic Cable Network, Automatic Block Signaling, ETCS L1/L2/L3, IOT based Diagnostic & PredictiveMaintenance systems etc.
The technological advancement is aimed toachieve high level of safety in trainoperations, availability of system andincreased speeds of trains with minimumhead ways. This ensures the efficient punctualoperation of Freight as well as of CoachingTrains. This has resulted in reduction ofturnaround in freight transportation. Withcontinuous and tireless effort of S&T verticalof RVNL in Railway Infrastructure, IndianRailways is able to achieve increase in freightloading and operation of large number ofpassenger trains across the length andbreadth of the country.
RVNL is a major contributor in providing EIinstallations on Indian Railways in connectionwith Doubling, 3rd Line, New Line and GaugeConversion. Keeping its tradition high, duringFY 2024-25, RVNL has commissioned ElectronicInterlockings at 47 Stations on Indian Railways.Besides new EIs, RVNL has commissionedmodification at 44 stations on IndianRailways to decongest Railways existingroutes.
In its commitment to Indian Railways, RVNLhas commissioned Major Yards of IndianRailways such as Yard remodeling ofAmbodala, Talcher Road, and Adityapurawith routes varying from 200 to 585 Routes.
RVNL has taken up 86 Nos. of Non-Interlocking(NIs) of stations for commissioning of Doubling& 3rd Line projects during the year. RVNL hasalso commissioned the 30 numbers of IBS,166 Automatic Signalling using ElectronicInterlocking and 41 Nos of mid-section levelcrossing gates have been interlocked withsignals to improve safety of road user. Notonly on the Signalling front, RVNL has alsocompleted the incredible achievement in thearea of telecommunication by providing 2763km of Fiber Optic Network and 6 Quad Cablenetwork during the year.
RVNL has increased team of IRSTELO licenseholders who are experienced to approveLogic & Interface Circuits and designdrawings of all types of Railway signalingsystems in-house. Besides, Railway Board hadentrusted RVNL to approve Logic & Interface
Circuits through 3rd Party IRSTELO licenseholders for CR, SCR, WR & WCR up to 75routes. So far, RVNL has checked Logic &Interface Circuits of more than 20 stations ofNCR icw 3rd line Automatic Block Signalling.This has reduced the workload of ZonalRailways on document approvalorganization and expedited the approvalprocess of Logic & Interface Circuits. This hasresulted in timely commissioning of largenumber of stations by RVNL to adhere thetarget set by Railway Board.
RVNL has commissioned latestCommunication-Based Train Control (CBTC)Signalling System from JOKA to MAJERHAT (10km UP & DN each) on Kolkata Metro .Similarily Communication-Based Train Control(CBTC) based Signalling System from KaviSubhash to Beliaghat (10 km UP & DN each)on Kolkata Metro is ready for commissioning.
RVNL has participated in various tenders ofAutomatic Signalling of Zonal Railways andhas been awarded Automatic Signallingworks of Rs 148.96 crore (SECR & SR) during FY2024-25.
RVNL has also participated in BSNL tender forDevelopment (Creation, Upgradation,Operation & Maintenance) of Middle MileNetwork of Bharat Net on Design BuildOperate & Maintain (DBOM) for UP East andUP West and has been awarded works worthRs 13235.56 crore during FY 2024-25.
Having played a very vital role in providinglarge nos. of signaling installations inconnection with large infrastructure projectson Indian Railway, Signaling &Telecommunication vertical is on the lookoutfor opportunities in various signalling andtelecom sector of Railways & other industrieswithin India & abroad.
There are 120 projects under various stagesof implementation by RVNL.
3.7.1 The details of 28 projects assigned by Ministryof Railways to RVNL till March 2025 and whichare under implementation are as under:
Name of Project
ER
Nabadwipghat-Nabadwipdham upto BB loop (9.58 km) {Part ofKalinarayanpur-Krishnanagar with Krishnanagar-Shantipur Nabadwip-ghat- GC, Krishnanagar-Chartala, MM for Krishnanagar Chapra-NL,Naihati-Ranaghat-3rd line, Nabadwipghat-Nabadwipdham upto BBloop (9.58 km), Ranaghat-Lalgola strengthening (bridge No.2)}
Dhanbad-Sonnagar (Patratu-Sonnagar) - 3rd line (291 km)
ECoR
Vizianagaram-Sambhalpur (Titlagarh) 3rd line
Mathura-Jhansi 3rd line
Bhatni - Aunrihar with electrification (125 km) (excl Indara -Mau (116.95 km))
Phephna-Indara, Mau-Shahganj (excl. Indara-Mau) (150.28 km) DL
SCR
Vijayawada-Gudur 3rd line
Kharagpur (Nimpura)-Adityapur 3rd line (132 km)
Hospet-Hubli-Londa-Tinaighat-Vasco da Gama (352.28 km)
Junagarh -Visavadar (42.28) km
Gauge
Conversion
CR
Yevatmal- Nanded (206 km) NL
Fatuah-Islampur incl. material modification for extension of newline from Neora to Daniawan; Daniawan to Biharsharif; Biharsharifto Barbigha; Barbigha to Sheikhpura
Rishikesh-Karnaprayag (125.09 km)
Bhanupalli-Bilaspur-Beri (63.1 km)
Dallirajhara-Rowghat (90 km) {Part of Dallirajhara-Jagdalpur (235 km)}
Indore-Jabalpur (342 km) NL sanctioned as Budhni-Indore (205 km)
CORE
Hospet - Hubli - Vasco da Gama (346 km)
Kazipet - Workshop for Wagon Periodical Overhauling
Repair of S&T Workshop at Podanur, Tamil Nadu
Samudragarh- Nabadwipdham - Road over bridge in lieu of levelcrossing No.14
National Rail & Transportation Institute at Vadodara (NAIR)
Construction of hostels in centralised training institutes (UmbrellaWork 2019-20)
Infrastructure up-gradation of Training Institutes at NAIR Campus
Direct Power Supply from Central Generating Agencies
OEW
Ghatkesar-Raigir (Yadadri)-Extension of multi modal transportationsystem Phase-II
MET
Baranagar-Barrackpore & Dakshineswar - Construction of MetroRailway (14.5 km)
Dum Dum Airport-New Garia via Rajerhat - Construction of MetroRailway (32 km) including Naupara (Ex.)-Baranagar (2.6 km) {Part ofDumdum-Baranagar Metro Railway sanctioned as MM to Dumdum-NewGaria Metro Railway vide letter No. 96/Proj/C/5/1/Pt. Dated 30.10.09]
Joka-Binoy Badal Dinesh Bagh via Majerhat - Construction of Metrorailway (16.72 km) incl material modification for extension fromJoka Diamond Park (Phase-I)
The details of 58 projects awarded to RVNL through competitive biddings up to March 2024 are as
i inHor
Agency/Client
MP Metro
Design and Construction of Elevated 10 km Viaduct and 09 ElevatedMetro Stations including all Civil, Structural, Roof structure, MEP works,Architectural finishes, Fagade, etc for Indore Metro Rail Project.
Metro
Works
Design and Construction of 07 Elevated Metro Stations includingStructures, Architectural Finishes, E&M Works etc. of Indore Metro RailProject.
NHIDCL
DPR Preparation for Highways in North-East Region in state ofNagaland for length of 200 KM.
DDC
DPR Preparation for Highways in North-East Region in state ofNagaland for length of 280 KM.
DPR Preparation for Highways in North-East Region in state of Mizoramfor length of 740 KM.
NFR
Construction of Single BG Tunnel Line No. 06 (approx. length 4930m)between Ch. 45800 to Ch. 50730 including Escape Tunnel (Total length4600m), in connection with DMV-Kohima new BG Line Project
Civil
GMRCL
Supply Installation Testing and Commissioning of Ballastless track (L -55 TKM) from Sarthana to Dream city in elevated and undergroundsection for corriodr -1, Surat Metro, Phase -II
NHAI
Construction Of 4 Laning of Nh-5 From Kaithlighat To Shakral Village(Shimla Bypass Package 1: From Km 128.835 To Km 146.300 For DesignLength=17.465km) In Himachal Pradesh On Hybrid Annuity Mode.
Construction of 4 lane highway from Samarlakota to AchampetaJunction (from km. 0.000 to Km. 12.250) as a part of Kakinada port toNH-16 connectivity in the State of Andhra Pradesh under BharatmalaPariyojana on EPC mode.
AMC
Development of Kharicut Canal (Between Naroda Smashan Gruh &Vinzol Vehla) in AMC area Pakage-2: Kharicut Canal DevelopmentNavyug School Canal Crossing to Nidhipark Society (Ch. 2500 - Ch.5000)
Development of Kharicut Canal (Between Naroda Smashan Gruh &Vinzol Vehla) in AMC area Pakage-3: Kharicut Canal DevelopmentNidhipark Society to Odhav Fire Station (Ch. 5000 - Ch. 7600)
GoG- NHDivision
Up gradation to Six Lane with Paved Shoulder of Sarkhej-ChangodarSection of NH 8A (New NH 47) from KM 11+950 to KM 16+000 on EPCmode in the State of Gujarat
CMRCL
Construction of Elevated Viaduct (approximate length of 10 km),nine (9) Elevated Metro Stations at Sholinganallur Lake-I, SriPonniamman Temple Sholinganallur Lake-II, Sathyabama UniversitySemmeancheri-I, Semmeancheri-II, Gandhi Nagar, Navallur, Siruseri,Siruseri Sipcot-1 And Siruseri SIPCOT-2 and stabling viaduct at SIPCOT
Construction of Bhesan Depot Cum Workshop Which Includes DCC,BCC and Associated E&M Works Under Corridor - C2, Bhesan To Saroli,For Surat Metro Rail Project Phase - 1, DC-2
Design, Supply, Erection, Testing and Commissioning for OHEModification Work in the existing 25 kV OHE for increasing speedpotential to 160 KMPH under East Central Railway Pradhankhanta -Bandhua Section of Dhanbad Division (DHN).
Electrical
MEA
Development of the UTF Harbour Project in Maldives
Southern
Provision of Automatic Block Signalling with Dual MSDAC, EI/OCinterface and Block Optimization in Arakkonam Junction(AJJ)-Nagari(NG) Section of Chennai (MAS) Division in Southern Railway (Reach-I).
S&T
Provision of Automatic Block Signaling with Dual MSDAC, EI/OCInterface and Block Optimization in NAGARI(NG) - TADUKU(TDK) sectionand Replacement of EI/RRI at VEPAGUNTA (VGA) Station of CHENNAI(MAS) Division in Southern Railway (Reach-II).
Provision of Automatic Block Signaling with Dual MSDAC, EI/OCInterface and Block Optimization in TADUKU(TDK)-RENIGUNTA (RU)section and Replacement of EI/RRI at TADUKU (TDK), PUDI (PUDI) & SRIVENKATA PERUMAL RAJU PURAM (SVF) Stations of CHENNAI (MAS)Division in Southern Railway (Reach-III).
MPPKVVCL
Commissioning of 33 kV Line associated works such as 33 kV LineBifurcation, 33 kV Line Interconnection and 33 kV Line ConductorAugmentation in Rewa, Satna, Sidhi, Singrauli, Sagar, Damoh,Chhatarpur, Panna and Tikamgarh Circles (Package-10) area ofMPPKVVCL, Jabalpur under Revamped - Reforms - Based and Results- Linked Distribution Sector Scheme
Supply, Erection, Testing and Commissioning of power SupplyReceiving & Distribution System, 750 V D Third Rail TractionElectrification and Scada system for Ahmedabad Metro
NWR
Provision of Automatic Block Signalling on Madar-Sakhun Section(51.13 Kms) of Jaipur Division over North Western Railway.
IR
Manufacturing cum Maintenance of 200 nos. of Vande BharatTrainsets including upgradation of the Government ManufacturingUnits & Trainsets Depots
Manuf
acturing
Madhya Pradesh Madhya Kshetra Vidyut Vitaran CompanyLimited||MPMKVVCL - Civil
Madhya Pradesh Poorva Kshetra: Revamped - Reforms - Based andResults - Linked Distribution Sector Scheme (RDSS) (Pkg-12)
Construction of 6-lane Greenfield Varanasi-Ranchi-Kolkata Highwayfrom Sonepurbigha village to junction with NH-22 (Chatra Bypass) nearChatra from km 184.700 to km 222.000 under Bharatmala Pariyojanain the state of Jharkhand on Hybrid Annuity Mode (Package 8).
Construction of Six Lane Elevated Kona Expressway from Km. 0.145to Km. 7.337 of NH-117 in the state of West Bengal on EPC mode
North
Central
Provision of EI based Automatic Signaling with continuous trackcircuiting and other associated works including suitable Indooralteration in Electronic Interlocking/RRI/PI stations enroute in Jhansi(incl)-Gwalior (Incl.) section of Jhansi Division of North Central Railway.
Supply, Erection, Testing and Commissioning of Power SupplyReceiving & Distribution System, 750 V Dc Third Rail TractionElectrification And Scada System For Surat Metro Rail Project Phase-I
HORC
C-4: Composite Contract package in connection with New BGRailway Line of HORC project for: (i) Design & Construction of TwinTunnel using NATM and Cut & Cover method from km 24.880 to km29.580; (ii) Design & Installation of Ballastless Track (excluding supplyof rails) from km 24.856 to km 29.680; (iii) Detailed Design, Supply,Installation, Testing & Commissioning of General Electrical Servicesincluding Supply, Erection, Testing and Commissioning of 11kV HT/LTPower and Control Cable Network, GIS Substation (11/0.433) kVA,Tunnel lighting system, etc. from km 24.880 to km 29.680; (iv) Design& Construction of Embankment, Bridges and other miscellaneousworks from km 12.00 to km 18.00.
MMRDA
Design, Manufacture, Supply, Installation, Testing and Commissioningof 2 nos. 110 kV receiving substation including 110 kV, 33kV & 25kVcabling work, complete 25kV overhead catenary system alongwithswitching station, 33kV auxiliary power distribution system including33/0.415 kV auxiliary sub-station (ASS) and complete SCADA systemfor main line & depot of Mumbai Metro line 2B of MMRDA. (IFB No:MMRDA/2B/MMRP/CA-40). Design, Manufacture, Supply, Installation,Testing and Commissioning of 2 nos. 110 kV
CMRL
Construction of Five (05) UG Stations at KMC(Kilpauk), Sterling Road,Nungambakkam, Gemini (Anna Flyover), Thousand Lights andThousand Lights Cross Over Box and works other than Diaphragmwall of Two UG Stations at Royapettah Chetpet Metro in C3 of CMRLPhase-II Project. UG-03
Construction of Four Underground Stations at Dr. Radhakrishan Salai,Thirumayilai, Mandaiveli and Adyar Junction and Two Cross PassageShafts and One Emergency Escape Shaft and works other thanDiaphragm wall of One Underground Stations at Greenways RoadMetro in Corridor-3 of CMRL Phase-II Project". UG -04
Construction of three (03) Underground Stations at Adyar Depot, IndiraNagar and Taramani Road Junction (Taramani) & Ramp and worksother than Diaphragm wall of One Underground Station atThiruvanmiyur Metro in Corridor-3 of CMRL Phase-II Project".-UG - 5
35
N.F. Railway
Engineering, Procurement, Construction of Design, Supply, Erection,Testing & Commissioning of 25 kV, 50 Hz, Single Phase, AC,Electrification OHE and TSS Works of Araria- Thakurganj New lineSection in connection with New Line Project of Araria- Galgalia ofN.F. Railway, including associated Works and Supply, erection,modification, testing and commissioning of SCADA for thesection.(106.958 RKM/119.27 TKM). (in EPC mode)(Tender No: EL-C-NFR-OHE-TSS-A-G-1RT3)
36
EDCL
Rwanda
Rawanda 008 - Transmission System Reinforcement and Last MileConnectivity Plant Design Supply and Installation of 45.8 KM (110 kVDouble Circuit Rukarara - Huye
Design, Manufacture, Supply, Installation, Testing and Commissioningof 2 nos. 110 kV receiving substation including 110 kV, 33 kV & 25 kVcabling work, complete 25 kV overhead catenary system alongwithswitching station, 33 kV auxiliary power distribution system including33/0.415 kV auxiliary sub-station (ASS) and complete SCADA systemfor main line & depot of Mumbai Metro line 2B of MMRDA. (IFB No:MMRDA/2B/MMRP/CA-40). Design, Manufacture, Supply, Installation,Testing and Commissioning of 2 nos. 110 kV
WATER
RESOURCES
ZONE,
UDAIPUR
Planning, Design and Construction of main Canal and Structuresincluding associated distribution system to provide Irrigation facilityto 41903 ha. area through Piped Irrigation Network for Upper High-Level Canal of Mahi Bajaj Sagar Project, Banswara (Raj) onEngineering, Procurement and Construction (E.P.C.) SingleResponsibility turnkey basis, including 10 years O&M.
Canal
South
Comprehensive Signalling and Telecommunication Works ForProvision Of Automatic Block Signalling System In Balharshah - MakudiSection of Secunderabad Division In South Central Railway.
Signalling
Supply, Installation, Testing and Commissioning of New 11 kV Lines, TransmissionLT Line on AB cable, Distribution Transformer Substation and Supporting Lineworks such as DPs, TPs, crossing etc. for separation of 11 kV Mix Feeders& Mix DTRs under Revamped Reforms-based and Results-linkedDistribution Sector (Package-16) in Chhatarpur circle of MPPKVVCL,
Jabalpur Company Area.
Supply, Installation, Testing and Commissioning of New 11 kV Lines,LT Line on AB cable, Distribution Transformer Substation and Supportingworks such as DPs, TPs, crossing etc. for separation of 11 kV Mix Feeders& Mix DTRs under Revamped Reforms-based and Results-linkedDistribution Sector (Package-17) in Seoni & Narsinghpur circle ofMPPKVVCL, Jabalpur Company Area.
Transmission
Line
MMRCL
Design and Construction of Elevated metro viaduct of length 6.92km between Ch. (-) 657.182 m to Ch. (-) 7576.78 m in reach 2A ofNMRP phase-2
Rehabilitation and Upgradation from 4 to 8 laning of Chandikhole -Paradip Section of NH-53 (Old NH - 5A) from km.60.000 to km.76.646(Package-4) in the State of Odisha on HAM mode - 2nd Call
MadhyaGujarat VijCompanyLimited
MADHYA GUJARAT VIJ COMPANY LTD.: Revamped - Reforms - Based Transmissionand Results - Linked Distribution Sector Scheme (RDSS) (Vadodara) Line
MADHYA GUJARAT VIJ COMPANY LTD.: Full Turnkey Contract (Design, TransmissionSupply and Installation) for Development of Distribution Infrastructure Linework for Loss Reduction at Dist. Dahod under Revamped Reforms-Based and Result-linked Distribution Sector Scheme
Construction of A) Six Elevated Metro Station viz. Pili Nadi to LekhaNagar in Reach-2A, B) One Elevated and one At-Grade station viz.Eco park and Metro City in Reach-1A respectively, C) At-Grade sectionFormation earthwork, boundary wall and retaining wall betweenCh. 19550 to Ch. 20421.016 & Ch. 20498.516 to Ch. 21296.917, D)Elevated Metro track supporting structure for Eco park Metro stationbetween Ch. 20421.016 to Ch. 20498.516 and E) Multi-Storied Buildingat Tulsi School Land (at Sitabuldi) of NMRP Phase-2
Western
All civil engineering works (Earthwork, Blanketing, Retaining Wall/Boundary Wall/Side Drain, Major Bridges, Minor Bridges and LHS/RUB,LCs, Construction of Station Buildings, Platform, Subways Cover overPlatforms, Staff Quarters, Passenger Amenities, Circulating Area,
Track Work
Approach Roads, Offices, Service Buildings, Watering, Sanitation,Protection Works etc. and Supply of 50 mm Machine Crushed StoneBallast, Complete track works including linking of Track works inconnection with Gauge Conversion work between Petlad - Bhadran(22.50 kms) of Vadodara Division on Western Railway.
All civil engineering works (Earthwork, Blanketing, Retaining Wall/Boundary Wall/Side Drain, Major Bridges, Minor Bridges and LHS/RUB,LCs, Construction of Station Buildings, Platform, Subways Cover overPlatforms, Staff Quarters, Passenger Amenities, Circulating Area,Approach Roads, Offices, Service Buildings, Watering, Sanitation,protection works etc. and Supply of 50 mm Machine Crushed StoneBallast, Complete track works including linking of Track works inconnection with Gauge Conversion work between Nadiad - Petlad(37.26 kms) of Vadodara Division on Western Railway.
Construction of 4 nos Tunnels (Total Length 1.6 km) with Ballast lesstrack, Earthwork in formation, Construction of Important Bridges(2 nos), Major Bridges (1no), Minor Bridges (25 nos), Supply of Stoneballast, Track linking, Side drain retaining wall etc. from km. 831.8 tokm. 841.9 in Dharakoh Maramjhiri section in connection with third line.
Tunnels
HPSEBL
Development of Distribution Infrastructure at SOUTH ZONE ofHimachal Pradesh under the Revamped Reforms-based and Results-linked, Distribution Sector Scheme [Loss Reduction Works]NIT/RFB No:CE(MM)/RDSS-(P-03)/SOUTH ZONE
Development of Distribution Infrastructure at NORTH ZONE ofHimachal Pradesh under the Revamped Reforms-based and Results-linked, Distribution Sector Scheme [Loss Reduction Works]
MPMRCL
Part Design and Construction of Elevated Viaduct, Five (5) ElevatedMetro Rail Stations (viz. Shaheed Bagh, Khajrana Chauraha, BengaliChauraha, Patrakar Colony & Palasia Chauraha) and Rampbetween Chainages 31+755 to 34+898.061 & 3+669.547 to 5+862 forIndore Metro Rail Project (Package IN-04)
IRSR
Varkala Sivagiri Railway station - Major upgradation/Redevelopement of Varkala Sivagiri Railway Station in Kerala
Infrastructure
Supply, Installation, Testing and Commissioning of 11 kV Lineassociated works such as 11 kV Line Bifurcation, 11 kV LineInterconnection, 11 kV Line Conductor Augmentation, LT AB CablingAugmentation and conversion of LT Bare conductor to AB Cablingunder Revamped Reforms-based and Results-linked Distribution Sector(Package-11) in Jabalpur (City), Jabalpur (O&M),Katni, Mandla,Dindori, Seoni, Chhindwara, Narsinghpur, Balaghat, Shahdol, Anuppurand Umariya Circles of MPPKVVCL, Jabalpur Company Area.
Supply, Installation, Testing and Commissioning of New 11 kV Line forBifurcation & Interconnection, Additional 11 kV Bay at 33/11 kV Sub¬station, Augmentation of conductor of 33 kV & 11 kV Lines, AdditionalDistribution Transformer Substations with associate New 11 kV Lines, LTLine on AB cable, Conversion of Bare LT line with AB Cable,Augmentation of LT AB Cable, Cover conductor for 11 kV Line CrossingAgriculture& Non Agriculture Feeder, 11 kv and 33 kv Bus Bar renovationother associated work, and Supporting works such as DPs, TPs, Crossingetc. in Jhabua O&M Division (LOT-12)under the Revamped Reforms-based and Results-linked, Distribution Sector Scheme
Construction of 220kV & 132kV Transmission Lines and associatedFeeder Bays on total Turnkey basis in Eastern MP
MMRCLPune Metro
Design and Construction of Elevated Viaduct of Length 4.519 kmsfrom CH: (-)1079.899 m to CH: (-)5599.298 m between PCMC andNIGDI (Bhakti Shakti) on the North-South Corridor of Pune MetroRail Project- Reachl - Extension.
RRVPNL
Supply & ETC of 132/33 kV Grid Sub-stations alongwith associatedLines & Bays
Signalling and Telecommunication work for provision of Automaticblock signaling on Khapri-Sewagram Section of Nagpur Division.Tender No. 55-2023-GSU-AUTO-KRISEGM
3.7.3 The list of 36 projects, awarded to RVNL through Competitive Bidding in 2024-25 and under executionis as under:
Agency /Client
IR SCR
Engineering, Procurement and Construction (EPC) Tender for"Proposed Doubling of Track between Ankai station (Excluding) atKm 16.00 (Ch 16000) & Karanjgaon Station (Excluding) at km 69.01(Ch69010) [i.e. (53.01 km)] including Electrification and Signaling worksin connection with Aurangabad-Ankai Doubling Project in NandedDivision of South Central Railway".
IR SR
Redevelopment of Thiruvananthapuram Central Railway Station (JVwith KRDCL)
IR SouthernRailway
Provision of Automatic Block Signaling System in Jolarpettai Junctionto Erode Junction of Salem Division in Southern Railway.
IR EasternRailway
Construction of Sitarampur bypass line under Asansol Division ofEastern Railway.
IR SouthEast CentralRailway
Provision of Auto Signalling with Electronic Interlocking (OFC Based)between Champa- Saragaon-Baraduar-Sakti section with alterationin existing Electronic Interlocking & Supply, Installation, Testing,Commissioning of new Electronic Interlocking, MSDAC & IPS etc.,execution of all indoor & outdoor works & construction andElectrification of the huts etc. in Champa-Sakti Section of BilaspurDivision of S.E.C. Railway.
NMRCL
Construction of 6 nos Elevated Metro Stations (Cantonment,Kamptee Police Station, Kamptee Municipal Council, DragonPalace, Golf Club And Kanhan River Metro Station) Between Ch.-7576.78 mm To Ch-13457.76 mm In Reach 2b of NMRP Phase 2
IR NorthCentralRailway
Provision of EI based Automatic Signaling with continuous trackcircuiting and other Associated works along with suitable indooralterations in Electronic interlocking/RRI/PI stations enroute inDhaulpur-Gwalior Section of Jhansi Division of North Central Railway
NTPC
PEA contract for execution of Balance Civil & HM works of BarrageComplex including part HRT package of Rammam Hydro ElectricProject Stage-III (3x40 MW).
Provision of Automatic Signalling on Ernakulam JN (ERS) - VallattolNagar (VTK) Section on B-Route of Thiruvananthapuram Division inSouthern Railway
OHE modification work for Up-gradation of existing 1 x 25 kV ElectricTraction System to 2 x 25 kV At Feeding System in Amla-NagpurSection in Nagpur Division of Central Railway to meet 3000 MTloading target.
Bangalore
Engineering, Supply, Erection, Testing and Commissioning of 33 kVDistribution, 750v DC Third Rail Traction Electrification IncludingTraction Sub-stations, Auxiliary Sub-stations and Scada System forPhase-2a & Phase-2b
East CoastRailway
Provision of Automatic Block Signaling System with dual MSDACand alteration in existing EI/PI/RRI stations in the section ofJakhapura-Nergundi, Khurda Road-Bhusundpur & Bhusundpur-Golanthra over Khurda Road Division of East Coast Railway. TenderNo. SNTPBBS-032024-JKPR-GTA
Design, Supply, Erection, Testing & Commissioning of 132 kV TractionSubstation, Sectioning Post (SPs), and Sub Sectioning Post (SSPs) in2x25 kV System on Rajkhaswan-Nayagarh-Bolani section ofChakradharpur division of South Eastern Railway to meet 3000MTloading target on EPC mode
OHE modification work for Up-gradation of existing 1 x 25 kV ElectricTraction System to 2 x 25 kV At Feeding System in Wardha-BallarshahSection in Nagpur Division of Central Railway to meet 3000 MTloading target
Design, Supply, Erection, Testing & Commissioning of 132 kV TractionSubstation Sectioning Post (SPs) and Sub Sectioning Post (SSPs) in2x25 kV System on Kharagpur - Bhadrak section of KharagpurDivision of South Eastern Railway to meet 3000MT
Himachal
zone
Development of Distribution Infrastructure at CENTRAL ZONE ofHimachal Pradesh under the Revamped Reforms-based and Results-linked, Distribution Sector Scheme [Loss Reduction Works]
Provision of MSDAC with existing DCTC at Stations (To serve as DualDetection) and replacing balance AFTCs in MAS-GDR & MSB-TBMautomatic block signalling sections of Chennai Division in SouthernRailway.
Design, Supply, Erection, Testing and Commissioning of 2x25 kVfeeder line along the track with 25 kV OHE modification works tomeet 3000 MT loading target for UP & DN line of Garwa Road -Mahadiya Section of Dhanbad Division under E.C. Railway (Total229/458 RKM/TKM).
3rd& 4th line between Jarapada & Talcher Road and Constructionof New line between Angul-Balram (MCRL Inner Corridor Phase-IDoubling 14 kms).: Execution of balance earthwork in formation,minor bridges, major bridges, P.way linking works, supply of ballast,S&T Buildings, Level Crossing and other Misc. works between Jarapadaand Talcher Road excluding station yards in connection with 3rd& 4thline of Jarapada-Budhapank Project and between Angul & Balramincluding yards of MCRL Inner Corridor Phase-I Doubling
Construction of (A) Elevated Metro Stations Seven Nos In Reach 3a,Namely (1) Hingna Mount View, (2) Rajiv Nagar, (3) Wanadongri,(4)Apmc,(5) Raipur, (6) Hingna Bus Station (7) Hingna,(B) Elevated MetroStations Three Nos In Reach 4a, Namely (1) Pardi,(2) Kapsi Khurd (3)Transport Nagar of NMRP Phase-2.
Design, Supply, Erection, Testing & Commissioning of Traction Sub¬stations with associated Switching Posts for upgradation work ofelectric traction system from 1 X 25 to 2 X 25 kV At feeding system inGomoh - Patratu Section of Dhanbad Division of East Central Railway
Engineering, Procurement and Construction (EPC) ContractAgreement for Doubling of Track between Parbhani to Parli stations(58.06 kms) (excluding Gangakhed yard from km 292.075 to km298.85 =6.775 km) including Electrification & Signaling works inconnection with Parbhani -Parli doubling project of South CentralRailway in the State of Maharashtra.
Earthwork in cutting and filling, blanketing, construction of minorbridges, major bridges, RUB, ROB, retaining wall, level crossing, sidedrain, catch water drain, P.way work and other ancillary worksfrom IR Ch. 205.000 km to 260.2 km between Kalipahari (inc.) toPradhankhuta (exc.) in connection with construction of Multi¬tracking Railway BG line.
BSNL
BHARAT SANCHAR NIGAM LIMITED (A Government of India Enterprise)-Bid Document for Development (Creation, Upgradation andOperation & Maintenance) of Middle mile network of BharatNet onDesign Build Operate and Maintain (DBOM) Model. Package No. -1to 8 OPEX (Operation & Maintenance) for 10 years for Pkg 3 & 6
BharatNet
KRIDE
Package C-4A: Construction of Nine (9 Nos.) Stations i.e. Elevated(1 No.) and At-Grade (8 Nos.) BSRP Stations of Corridor-4A atHeelalige, Singena Agrahara, Huskur, Ambedkar Nagar,Carmelaram, Bellandur, Marathahalli, Doddanakundi,Kaggadasapura including Civil, Structural, Entry/Exit Structure, SteelFOB, Roof Structures, PEB, works Architectural finishes and E&M Worksand Detailed Design & Engineering (DDE) with all associated worksfor Bengaluru Suburban Rail Project"(BSRP)"
SCR Construction Organization: Engineering ProcurementConstruction (EPC) Contract of Doubling of Track between Navipetstation (Excl) From km 446.900 to Indalvai Station (Incl.) km 482.900(33.70 km), {Excluding Nizamabad Yard from km 458.825 to 461.125(i.e.) 2.3 Km} including Electrification & Signaling works in of South¬Central Railway in connection with Mudkhed-Medchal DoublingProject in the State of Telangana.
Punjab RDSS
Development of Distribution Infrastructure Work for Package-3Central Zone for Execution of Ht/Lt Infrastructure Loss ReductionWorks Under Reforms-Based and Results-Linked, RevampedDistribution Sector Scheme (RDSS) In the State of Punjab.
Design, Supply, Erection, Testing & Commissioning of 132/55 kVTraction Substation, Sectioning Post (SPs) and Sub Sectioning post(SSPs) in 2 x 25 kV Traction System (Scott Connected Transformer) ofBhusaval - Khandwa Sections of Central Railway, to meet 3000 MTloading target on EPC mode.
Koraput-Singapur Road Doubling Project: Execution of 27 Nos ofMajor Bridges i.e. (22 Nos of Major Bridges & 5 Nos of ROBs) andearth work in formation of approaches, protection works and otherconnected miscellaneous works between Tikiri and Bhalumaskastations in connection with Koraput-Singapur Road DoublingProject of Waltair Divison, East Coast Railway
Design, Supply, Erection, Testing and Commissioning for upgradationof Electric traction system from 1 x 25 kV to 2 x 25 kV traction system forKharagpur(Excl.)-Tatanagar(Incl.) section of Kharagpur/Chakradharpurdivision of South Eastern Railway to meet 3000 MT loading target.
Survey, Design, Supply, Installation, Testing and Commissioning ofKAVACH equipment and other associated works over 790 RKM ofHubballi & Mysuru Divisions of South Western Railway.
Engineering, Procurement and Construction (EPC) for Design, Supply,Erection, Testing, Commissioning of 2x25 kV OHE & PSI System (TSSS,SPS & SSPS) Including Electrical General Services, Engineering &Telecommunication Works Between Rayadurga (Excl.) (Ch: 205/463)To Pavagada (Incl.) (Ch: 106/000) of TK-RDG Section (99.463 rkm/114.145 tkm)
Construction of six lane connectivity to Visakhapatnam Port Roadfrom km 0.000 (Sabbavaram bypass of Anakapalli - Anandapuramcorridor) to km 12.660 (Sheela nagar junction) of NH 516C on HybridAnnuity Mode in the State of Andhra Pradesh under NH(O)
Road
OHE Modification Work for Up-gradation of existing 1x25 kV ElectricTraction System to 2x25 kV At Feeding System in Itarsi - Amla Sectionin Nagpur Division of Central Railway to meet 3000 MT Loading Target.
SOUTHEASTERN RLY
Design, Supply, Erection, Testing and Commissioning for upgradationof Electric traction system from 1 x 25 KV to 2 x 25 KV traction systemfor Rajkharsawan - Nayagarh- Bolani section of Chakradharpurdivision of South Eastern Railway to meet 3000 MT loading target.(Tender No: SER-OHE-RKSN-NYG-2x25KV)
Design, Supply, Erection, Testing and Commissioning for upgradationof Electric traction system from 1 x 25 KV to 2 x 25 KV traction systemfor Kharagpur (Excl.)-Bhadrak (Excl.) section of Kharagpur divisionof South Eastern Railway to meet 3000 MT loading targetTender No:SER-OHE-KGP-BHC-2x25KV
3.7.4 The list of projects transferred back to Railway in 2024-25 is as under:
Dankuni-Furfura Sharif NL {Part of Liluah-Dankuni - 3rd line(10.13 km) with extension to Furfura Sharif}
Provision of Addl. Traction Substation at Budhni
Khijadiya-Visavadar GC (91.27 km)
Veraval-Talala-Visavadar GC (71.95 km)
Setting Up of Centralised Training Institute for IRSME & IRSS Officersat Lucknow
Rail Vikas Nigam Limited (RVNL) has beenawarded three major packages (IN02, IN03& IN04) of the yellow line of the project asdetailed under:
Package 02-
Design and Construction of Elevated MetroRail Stations including all Civil, Structural, Roofstructure, MEP works, Architectural finishes,Facade, Entry/Exits, FOB, Viaduct within thestations including Transition spans - IndoreMetro Rail Project Yellow Line. (7 no. ofElevated Metro Stations)
Package 03-
Design and Construction of Elevated Viaduct,Viaduct Connecting Depot leading up tointerface location, Elevated Metro RailStations including all Civil, Structural, Roofstructure, MEP works, Architectural finishes,Facade, Entry/Exits, FOB, Viaduct within thestations including Transition spans - IndoreMetro Rail Project Yellow Line.
(10.9 km Viaduct & 9 no. of Elevated MetroStations)
Package 04-
"Part Design and Construction of ElevatedViaduct, Five (5) Elevated Metro Rail Stations
(viz. Shaheed Bagh, Khajrana Chauraha,Bengali Chauraha, Patrakar Colony & PalasiaChauraha) and Ramp between Chainages31+755 to 34+898.061 & 3+669.547 to 5+862for Indore Metro Rail Project".
(4.73 km Viaduct & 5 no. of Elevated MetroStations)
? After completion of work of 5.8 km viaductand 5 elevated metro station in Dec'24, theCMRS was successfully carried out in 3 stages:
V CMRS rolling stock: 22nd Jan 2025
V Dy. CMRS inspection: 10th & 11th Feb
2025
V CMRS inspection for 24th & 25th
works: March 2025
Accordingly, authorization for commercialoperations was received for 5.8 km viaductand 5 elevated metro station.
? Overall Work of 10.8 km viaduct out of 10.927km completed.
Key Features of the Project
Project consist of 3 Packages named asPackage IN-02, Package IN-03 & Package IN-04, the key features of the areas under:
Package-2 includes 7 nos. of Elevated Metro Stations (ISBT/MR10 flyover, Chandragupta Square,Hira Nagar, Bapat Square, Meghdoot Garden, Vijaynagar Square, Radisson Square) & transitionspans.
Description
Unit
IN-02
Alignment - Stations
KM
1.050
Elevated Stations
No's
Package-3 includes 9 nos. of Elevated Metro Stations (Gandhi Nagar, Super Corridor 6, Super Corridor5, Super Corridor 4, Super Corridor 3, Super Corridor 2, Super Corridor 1, Bhawarsala, MR10 Roadstation) & 10.9 km of elevated viaduct (Elevated Viaduct, viaduct connecting Depot leading upto interface location).
IN-03
Route length
10.927
Package-4 includes 5 nos. of Elevated MetroRail Stations (viz. Shaheed Bagh, KhajranaChauraha, Bengali Chauraha, PatrakarColony & Palasia Chauraha) and Rampbetween Chainages 31+755 to 34+898.061& 3+669.547 to 5+862.
4.736 km of elevated viaduct.
JV (RVNL-URCC) [51-49]
IN-04
4.736
RVNL has won 3 contracts on bidding with Chennai Metro Rail Limited (CMRL) as part of it'smassive Phase - II expansion in the year 2023 comprising Construction of 16 underground stationsspread over 3 contract packages.
Package
Stations
Status
UG03
Kilpauk, Sterling Road, Nungambakkam,Gemini (Anna Flyover), 1000 Lights,Chetpet, Royapettah - 7 Stations
Diaphragm wall & slab works in progress.Utility diversion works nearing completion.
UG04
RK Salai, Thirumayilai (C3 & C4), Mandaiveli,Greenways Road, Adyar Junction - 5 Stations
UG05
Adyar Depot, Indira Nagar, Tiruvanmiyur,Taramani Road Junction - 4 Stations
Diaphragm wall & Utility diversion worksin progress.
16 stations
All the 3 projects are progressing as per the timelines. The project includes some of the deepeststations on the Chennai metro network and are being executed in the heart of the city. Theprojects on completion are destined to transform the city of Chennai the significant contributionof RVNL in shaping the urban infrastructure will be recorded & recognized as a Nation buildingexercise.
UG-04 - RK SALAI STATION (North shaft Roof slab casting in progress)
The List of machineries mobilized for each package
as on date is as follows:
Min Requirement
Actual Mobilization
Trench Cutter
GRAB
Piling Rig
UG - 3
UG - 4
UG - 5
15
3.8.3 Nagpur Metro Projects - Design & Construction of 6.92 km Elevated Metro Viaduct, 24 ElevatedStation in Nagpur Metro Rail Project - Phase - II.
Project Brief: -
RVNL is entrusted with 6.92 km viaduct and 24 number of stations for Phase 2 Works in NagpurMetro for a total assigned value of Rs 1108.43 Cr.
Work is going on in full swing in all packages.Major package pertains to construction of6.92 km Viaduct (Only Civil Portion). Itinvolves 238 number of spans. Around 45% ofthis package is complete. Launching of 56spans (total 1.75 km) with 3 no's of LGs hasbeen completed till date.
This package also involves construction of210 mtr of CLC with central span of 110 mtrover railway lines which is longest in NagpurMetro. Total duration of work is 30 monthsfrom 06-Oct-23 and it is targeted to becompleted within DOC.
Major Structure Details
Sl No
Structure Details
Qty
Box Culverts
27 Nos
Minor Bridges
6 Nos
Via Duct
1 No (1.7km)
Fly Over
1 No (0.45km)
SVUP (1 x 7)
3 Nos
LVUP (1 x 12)
2 Nos
VUP (1 x 30)
1 No
1 No (0.1km)
Major Junctions
Station Works are covered under 3 differentPackages (i.e. Reach 2A,1A, 2B, 3A & 4A) andwork is going on with desired pace in allpackages with heavy deployment of Menand Machineries.
Under Bharatmala pariyojana, RVNL PIU/Waltair is executing the 12.25 km 4-lanehighway from Samarlakota to Achampetajunction as a part of port connectivity roadfrom Kakinada port to NH-16 (Kolkata-Chennai). Completion of this project willenhance logistic efficiency and reducelogistics costs of freight movements.
Project Data
LOA Issued
29-09-2022
Agreement Signed Date
01-05-2023
Appointed Date
17-08-2023
Project Completion Date
15-08-2025
Project Duration
24 Months fromAppointed Date
S.No.
Scope
Completed
Embankment (Gravel)
Cum
3,32,955
1,33,141
RE wall (Pond ash)
3,56,685
2,71,522
Sub grade
2,30,217
64,903
Work in progress
VUP
LVUP
SVUP
27
16
CTSB
Km
9.74
3.917
CTB
3.911
WMM
3.956
DBM
3.64
BC
REWallpanels Casting
Sqm
40,000
36,931
REWallpanels Erection
6209
19
RCCDrain(2Lane)
2.154
20
Structural steel
MT
1300
Kharicut canal is 137 years old canal systemcatering 10200 ha command area fordisposal of rain and storm water fromupstream catchment area betweenSabarmati and Khari rivers and also used forirrigation purpose. Approximate 23 kmlength of Kharicut canal which was passingthrough agricultural land and surroundingvillages of Ahmedabad City is now passingthrough the dense eastern part ofAhmedabad city.
The work of development of the KharicutCanal was awarded by AMC on 19.10.2022& RVNL's scope of work covers a total lengthof 5.1 km, falling under Package 2 & 3, fromchainage 2500 to 7600. The primary objectiveof this project is to improve theenvironmental and sanitary conditions forresidents living along the canal byeliminating unhygienic and foul-smellingsurroundings, thereby reducing the risk ofdiseases. Additionally, the canal alignmenthas been integrated with a four-lane road,aimed at easing traffic congestion andimproving urban mobility. The overall physicalprogress is approximately 90%.
Construction of diaphragm walls (D-walls) on both sides of the canal forstructural support.
Construction of Storm Water Drain (SWD)boxes of size 6 m x 3.6 m on both sides.
Installation of precast box segments(2.60 m x 2.60 m x 1.5 m) in the centralportion of the canal.
Road construction over the canalconsisting of Wet Mix Macadam (WMM)base layer, Dense Bituminous Macadam(DBM) intermediate layer, BituminousConcrete (BC) top layer.
Landscaping with plantation in thecentral median to enhance aesthetics.
RCC pipelines and inlet chambers onboth outer sides to manage localdrainage effectively.
Street lighting provided on both sidesfor the safety and convenience ofpedestrians and vehicular traffic.
In summary, the Kharicut CanalDevelopment Project significantly contributesto a cleaner and healthier environment whilealso improving transportation infrastructurefor the benefit of the city's residents.
Before (Old canal)
The agreement for manufacturing VandeBharat Sleeper version train was signed on 27September 2023 between Indian Railwaysand the JV of JSC Metrovagonmash, RVNLand JSC Locomotive Electronics System (LES)since promoted and incorporated as KinetRailway Solutions Ltd. (KRSL).
Vande Bharat sleeper train will have 16coaches which includes 11 AC 3-Tier coaches,
After Development Work
4 AC Two-Tier coaches and 1 First AC. It willbe equipped with advanced features suchas special roofing, enhanced airconditioning, virus control mechanisms,reduced jerks, noise, and vibrations. Theproject envisages meticulous design ofaesthetically appealing interiors and theselection of suitable inside panels in order toproduce significantly improved version thatsets new standard of excellence & innovation,demonstrating an unwavering commitmentto excellence and innovation in railtransportation.
RVNL bagged the first offshore order fordevelopment of a port and construction ofallied infrastructure in Maldives, i.e. fordevelopment of UTF (Uthuru Thila Falhu- Island)Harbour Project. This is a strategic project ofGovernment of India. The agreement wassigned in January 2023.
The work has taken off well. As on date, thephysical progress is 45%, 75% of marine and10% of land side works have been completed.
Rail Vikas Nigam Limited (RVNL), wasentrusted with the responsibility ofconstruction of New Pamban Bridge in 2019.As the nodal agency for this ambitiousinfrastructure project, RVNL's role extendedfrom concept to commissioning and not amere construction of new bridge. RVNLcommitment was to deliver a structure thatwould not only meet the needs of the presentbut also preserve region's connectivity andeconomic vitality for time to come. Thus, theproject was not merely a replacement to anold bridge, it was about setting a newbenchmark in modern bridge engineering.
The New Pamban Bridge is designed as avertical lift structure with cables/pulleyarrangement with advanced geotechnicalstudies, hydrodynamic analysis, and the useof durable corrosion-resistant materials, weensured the longevity and strength of thestructure. We also used modern constructiontechniques to speed up the process whileensuring the highest levels of quality control.
The construction of the New Pamban Bridgepresented numerous challenges, ranging fromenvironmental obstacles to logisticalcomplexities. The Palk Strait's turbulentwaters, strong winds, and unpredictableweather patterns created difficulties in theconstruction process. Additionally, theregion's susceptibility to cyclones and seismicactivity necessitated careful planning androbust design.
Logistically, transporting heavy materials tothe remote construction site posed anotherchallenge. The narrow windows of
opportunity provided by the tides had to bemaximized to facilitate the timely delivery ofmaterials. Despite these hurdles, the team ofengineers and workers displayed exceptionalingenuity innovative solutions, cutting-edgetechnology, and sheer determinationovercoming the challenges and therebyensuring the successful completion of thebridge.
It is a matter of great pride that doing thecourse of work involving more than 1400 tonsof fabrication, launching of lift spans and 99Girders, the whole work was absolutely injuryfree. This is testimony to RVNL's workingmethods taking utmost care for safety andhealth.
The Iconic Pamban Bridge was inauguratedby Hon'ble Prime Minister of India.
Total Length of Bridge : 2.08 km
Span Configuration
99x18.30m
+ 1x72.50m
Weight of Lift span
652 T
Weight of Towers
760 T
Weight of each Counterweight
310 T
Height of Tower
34.80 m
Lift Height
17 m
Lifting Time
5 min30 Sec
• Stainless steel reinforcement used infoundation/ Sub-structure.
• 19.65 m long steel plates to eliminatesplice joint in the approach span girdersof 18.3 m span.
• Fully welded girder (Box sections) isadopted for lift span truss to minimizethe corrosion.
• 20 m long rails 60 kg to reduce rail joints.
• Robust Painting Scheme adopted -design life - 38 years.
• Piling by gantry method on Mandapamend due to shallow depth.
• Complete automation of lifting/monitoring (SCADA).
This transformative project in Uttarakhand isbeing executed by RVNL. It will connect thestate's remote hinterlands directly by rail,marking a new chapter in regionalconnectivity and development. The projectspans 125 kms, and the route is chartedthrough the challenging Himalayan terrain.The project comprises 12 new stations 28tunnels with a cumulative tunnel length of213 kms and 19 major rail bridges, making itone of the most challenging projects currentlyunderway in India. This line may also serve asthe main feeder route for any futureChardham connectivity.
The first block section, a 5.7 km stretchbetween Virbhadra and Yog Nagri Rishikesh,was successfully completed and
commissioned in March 2020. Of the total 213kms of tunnel excavation planned, 193 kmhave already been completed, along with82 km of final lining. 8 out of the 19 major railbridges have been completed, ensuring vitalconnectivity across difficult river crossings andvalleys. In addition, four key road bridges havebeen constructed to facilitate access to worksites and future stations. Of the 46 tunnel drivesplanned, 35 breakthroughs have beensuccessfully achieved.
The New Line is expected to be a catalyst forthe socio economic development of theregion and will considerably reduce traveltime. The breakthrough of 14.57-km-longtunnel no 8 between Devprayag and Janasuwas witnessed by Hon'ble Railway Minister.This is the India's longest transportationtunnel.
The 63 km long Railway line passes throughthe challenging hill terrain of the lowerHimalayas with a total route tunneling of 25.9km. The proposed electrified BG rail line shallenable regional development through theconnectivity of Himachal Pradesh with thenational railway network and will act as agateway to connect with the internationalborders towards Leh for strategic purposes.
3.9.4.1 Indian Railways transferred the works of fourmajor projects for extension of KolkataMetro to RVNL in March 2010 viz.
• Joka-BBD Bag via Majerhat (16.72 km)
• Dum Dum Airport-New Garia viaRajarhat (32 km)
• Baranagar-Barrackpore& Dakshineswar(14.5 km)
• Noapara (Ex.)-Baranagar (2.6 km)
3.9.4.2 Thereon RVNL was entrusted to build Metrocorridors of about 65 km in Kolkata withoutany survey of underground utilities andwithout any DPR (Detailed Project Report).The issues like removal of encroachmentsand relocation of utilities along with delayin availability of traffic diversion haveaffected the execution. RVNL has taken allpossible action for implementation andearly commissioning of Metro projects forlarger interest of people of Kolkata.
3.9.4.3 The foundation stone for Joka-BBD Bagproject was laid by Her Excellency, Presidentof India on 22.01.2010. Subsequently, 2
packages for viaduct and 2 packages forstations were awarded in December 2010and April 2012 respectively. This entire Metrocorridor has been planned in 3 phases i.e.in 1st phase from Joka to Majerhat elevatedsection and in the 2nd phase from Majerhatto Mominpur, in 3rd phase from Mominrurto Esplanade station as undergroundsection. Originally sanctioned as elevatedsection but Material Modification issanctioned by Ministry of Railways forunderground system from Mominpore toEsplanade. For construction of Mominpurstation, working permission from Army HQhas been received only on 20.03.2023 andwork going on full swing.
In the Metro corridor from Joka to Majerhat,from Joka to Taratala (Phase-I) 6.50 km hasbeen inaugurated by Hon'ble Prime Ministeron 30.12.2022 & commercial services startedby Metro Railway on 02.01.2023. Anotherphase of 1.25 km from Taratala to Majerhathas been inaugurated by Hon'ble PrimeMinister on 06.03.2024 & commercialservices started by Metro Railway has beencommenced from 15.03.2024. The stationover yard at Majerhat is on three layers.Beyond Majerhat, the Joka to MajerhatMetro Corridor is being extended uptoEsplanade going underground fromMominpore ramp. The Works contract forthe underground section has beenawarded and the works of undergroundportion has been started. Workingpermission has accorded after Hon'ble HighCourt/ Kolkata's clearance for execution
in Defence land in the Maidan area for thepublic interest of Kolkata. The NOC fromVictoria Memorial Trust has been receivedrecently to go ahead with undergroundstation near Victoria Memorial.
Since this Metro stretch is a standalonesystem, a Maintenance Depot has beendeveloped in Joka and Ph-I part is underoperation. Earlier, due to non-availabilityof land (24.48 hectare), the tender for thedepot was discharged twice, once inFebruary 2013 and again on October 2017.Thus, the commissioning is planned in 3phases i.e (a)Ph-I-Joka-Taratala, (b)Ph-II-Taratala-Majerhat, (c) Ph-III- Majerhat-Esplanade. After starting of commercialservices of 1st & 2nd phase commissioningthe outskirt population of Kolkata has beenconnected to Kolkata which is a great relieffor the people residing away from Kolkatabut normally come to Kolkata on daily basisdoing a tough journey every day. Presentlyland for construction of cut and coverbetween Mominpur station and Khidirporestation and land for Khidirpore station is notmade available by Kolkata Armed Policeand Nepal Consulate at Kolkata.
In the section of New Garia to RabindraTirtha of Dum Dum Airport-New Gariaproject, initially 4 packages of Viaduct wereawarded on 21.10.2011. About 20 kmviaduct has been completed. Thecontracts for 21 stations (3 packages) wereawarded on 05.03.2014. Out of 21 stations,station land for Technopolis Metro stationis now handed over. The project gotdelayed because of issues relating to landacquisition, traffic diversion, utility diversion
and other permission over busy EM Bypassroad. Further, change of alignmentproposed by State Government whereunauthorized buildings were constructedeven after the Gazette Notification forMetro construction, and other impedimentslike shifting of markets, traffic guard, raisingof 220 kV overhead line, removal ofencroachments, etc. slowed down theprogress of work. Substantial part of theseimpediments have been either removedand the balance are on the way of beingremoved. The alignment from City Centre-II to Airport is now approved by StateGovernment after long persuasion andcontract for construction of Metro beyondTitumir to Airport has been awarded on18.01.2021, the work is under progress. In thissection the commissioning was planned in3 phases phases earlier i.e (a)Ph-I-NewGaria-Hemanta Mukhopadhyay, (b)Ph-II-Hemanta Mukhopadhyay to Salt LakeSector-V and (c) Ph-III- Salt Lake Sector-V toAirport. Due to unavailable work front invarious stretches of the corridor andconsidering commissioning point of viewthe phases were revised i.e. (a)Ph-I-NewGaria-Hemanta Mukhopadhyay, (b)Ph-II-Hemanta Mukhopadhyay to Beleghata, (c)Ph-III Beleghata to Salt Lake Sector-V and(d) Ph-IV- Salt Lake Sector-V to City Centre 2and (e)Ph-V City Centre 2 to Airport.
Now in present scenario, (a) Ph-I-New Garia-Hemanta Mukhopadhyay (5.4km)commercial run has been started from15.03.2024 after being dedicated to thenation by the Hon’ble Prime Minister on
06.03.2024, (b) Ph-II-Hemanta Mukhopadhyayto Beleghata (4.46 km) CCRS Inspection hasbeen conducted on 28.03.2024 &
29.03.2024, (c) Ph-III Beleghata to Salt Lake
Sector-V was planned for commission inDec'2024, however due to non-availabilityof traffic diversion block betweenBelaghata to Gour Kishore Ghosh stations,work of launching of viaduct is held upsince Feb 2025. It will take 5-6 months tocomplete the remaining work once thetraffic diversion is allowed by Kolkata Policeand Bidhan Nagar Police. Balance 02 phasei.e. (d) Ph-IV- Salt Lake Sector-V to CityCentre 2 has been planned for commissionin Dec'2025 and (e)Ph-V City Centre 2 toAirport are planned for commission uptoMar'2026.
For Baranagar-Barrackpore & Dakshineswarand Noapara-Baranagar, the work wasplanned in 2 phases i.e. the first phase
being Noapara-Baranagar-Dakshineswarand in the second phase, from Baranagar-Barrackpore. The first phase, i.e. fromNoapara to Dakshineswar, the Metrocorridor has been inaugurated anddedicated to the Nation by Hon'ble PrimeMinister on 22.02.2021 for public use.
For the second phase of this Metro corridor,i.e. Baranagar-Barrackpore, a MoU wassigned between State Government, MetroRailway and RVNL in October 2011. Originalsanctioned alignment via B.T. Road was notagreed by State Govt. despite signing ofthe MoU in Oct' 2011 for closing of 2pipelines and even after completion of newpipeline work of 64" dia by State Govt.Repeated observations raised by KMC havebeen complied by RVNL. However,technical approval/NOC from State Govt.is still awaited.
project has been inaugurated by Hon'ble PMon 22.02.2021 and Commercial Operation oftrain service started w.e.f. 23.02.2021.
(ii) Joka-Taratala in Joka - Esplanade MetroCorridor: 9.0 km of continuous stretch fromJoka Depot has been completed. Majorstructures and stations have been completedat Joka, Thakurpukur, Shaker Bazar, BehalaChowrasta, Behala Bazaar, Taratala. The firstphase i.e. Joka to Taratala of Joka-EsplanadeSection has been inaugurated by Hon'blePrime Minister on 30.12.2022 andcommissioned on the same day.
(iii) Taratala-Maierhat Joka - Esplanade MetroCorridor: 2nd phase of 1.25 km has beeninaugurated by Hon'ble PM on 06.03.2024 andCommercial Operation of train servicestarted w.e.f. 15.03.2024.
(iv) New Garia-Hemanta Mukhopadhvav in NewGaria-Airport corridor: 5.4 km has beeninaugurated by Hon'ble PM on 06.03.2024 andCommercial Operation of train servicestarted w.e.f. 15.03.2024.
(v) Hemanta Mukhopadhvav to Beleghata inNew Garia-Airport corridor: 4.4 km of stretchtowards Beleghata from HemantaMukhopadhyay, CRS inspection has beenconducted on 28.04.2024 & 29.04.2024,authorization is received on 12.06.2024.
During 2024-25, no accident was reportedfrom any of the project sites of RVNL.
The first ADB loan (IND-1981) sanctioned for"Railway Sector Improvement" was closedon 31.12.2011. A 2nd ADB Loan has beensanctioned for funding of 5 projects, namely:
• Raipur-Titlagarh doubling
• Sambalpur-Titlagarh doubling
• Hospet-Tinaighat doubling
• Daund-Gulbarga doubling
• Pune-Guntakal Railway Electrification
The funding by ADB requires compliance ofvarious loan covenants on resettlement andrehabilitation of project affected persons,procurement of works and stores following
international competitive bidding andimplementation of plans for mitigation ofsocial and environmental impact norms. AMulti Tranche Financing Facility of $ 500 millionhas been agreed to by ADB. The loanagreement for first Tranche (Loan No. 2793-IND) of this MFF for an amount of $ 150 millionwas signed in July 2012 and the loanagreement for second Tranche (Loan No.3108-IND) of this MFF for an amount of $ 130million was signed in February 2014, the loanwas closed on 20.12.2019. Project Agreement& Loan Agreement against ADB loan No.3623-IND (Railway Sector InvestmentProgram- Tranche III) for an amount of $ 130million have been signed on 16.3.2018 andmade effective on 07.06.2018. The loan wasfully disbursed on 29th October 2021 and theloan account was closed effective on 2ndDecember 2021. Project Completion Report(PCR) submitted to ADB and loan is fullyclosed.
As the size of projects being executed by RVNLis quite large, to ensure fast award andexecution of projects, RVNL invites tendersconsisting of multiple packages. Each tendermay consist of upto 3 contract packages. Thisapproach has a number of advantages suchas:
a) Multiple contracts can be awardedthrough one tender which saves timeand effort in invitation and finalizationof tenders.
b) Both small and large agencies cancompete for any contract packagewhich increases competition.
c) Large agencies who are capable ofexecuting big contracts can quote formultiple packages to achieve economyof scale and pass on the benefit to RVNLby quoting discounts in case of awardof more than one package.
d) Smaller agencies, which would not beeligible to quote if the tender for theproject was floated in a single package,are now able to compete in any of thecontract packages individually as theymay meet the qualification requirementsof individual packages which are ofcomparatively smaller value.
During 2024-25, contracts worthapproximately Rs. 5520.32 Cr. were awarded.
The following major contracts were awardedby the Company during the year:
Construction of Tunnel T1 from Chainage km33+160 To km 34+400 And Tunnel 2 fromChainage km 57+400 to km 66+040 withBallast Less Track and Works Related toFormation on Approaches of such Tunnels inconnection with Construction of ElectrifiedNew BG Railway Line Between Mangliyagaon(Indore) to Budni Stations (198 kms) of RatlamDivision and Bhopal Division of WesternRailway and West Central Railwayrespectively in Madhya Pradesh State, India.(Rs. 872.70 Crore)
Design, Supply, Installation, Testing andCommissioning of Broad Gauge BallastlessTrack (BLT), Supply of Ballast and Installationof Track (Excluding Supply of Rails and TrackSleepers) between Chainage 6+015 (Fls) To125+200 (Fls) in connection with New BG Linebetween Rishikesh and Karanprayag (125 km)in the State of Uttarakhand, India. (Rs. 750.83Crore)
Construction for Tunnels & Formation worksfor Military sidings & approach inKaranprayag yard in connection with newBG line between Rishikesh and Karanprayag(125 km) in the state of Uttarakhand, India.(Rs. 611.05 Crore)
Package-1A: Construction of Roadbed,Minor Bridges, Buildings, Installation of Track(Excluding Supply of Rails, Sleeper & ThickWeb Switches), And Other Civil EngineeringAnd General Electrical Works In ConnectionWith New Bg Railway Line BetweenMangliyagaon-Kheri (Incl) Stations(Chainages 0.000 - 57.400 km) In Indore-BudniSection of Ratlam And Bhopal Divisions OfWestern Railway And West Central RailwayRespectively In Madhya Pradesh State, India(Rs. 436.73 Crore)
Package IIIB Construction of Road Bed, MajorBridges, Minor Bridges, ROBs, RUBs, includingroad approaches, Station Buildings, Staff Qtrs,Other Service Buildings, HL Platforms, COPs,FOBs, General electrical work and other worksrelated to construction of Yavatmal- NandedNew BG Line from km: 190 to km: 207 ofCentral Railway in Maharashtra Stateincluding construction of three tunnels: T3 (370m), T4 (440 m) & T5 (2630 m) with BLT in tunnels.(Rs. 423.10 Crore)
Construction of Roadbed, Major and MinorBridges and Track Linking (excluding Supply
of Rails and Sleepers); S&T; OHE & GeneralElectrical Works in connection with Extensionof MMTS phase-II from Ghatkesar (km. 213.840)(including) to Wangapalli (km. 252.300)(including) on Secunderabad- Kazipetsection in Secunderabad Division of SouthCentral Railway, Telangana State, India. (Rs.416.75crore)
Package IIIB Construction of Road Bed, MajorBridges, Minor Bridges, ROBs, RUBs, includingRoad Approaches, Station Buildings, StaffQtrs, Other Service Buildings, HL Platforms,COPs, FOBs, General Electrical Work andother works related to Construction ofYavatmal-Nanded New BG Line from km: 190to km: 207 of Central Railway in MaharashtraState including construction of three tunnels:T3 (370 m), T4 (440 m) & T5 (2630 m) with BLT intunnels. (Rs. 313.55 crore)
Package-2: Design, Supply, Erection, Testingand Commissioning of 220 kV, 3-Phase D/Ctransmission line (14.3 km) from Raigarh(PGCIL GSS ) to Raigarh TSS, Raigarh TSS toKharsia TSS (33 km), Kharsia TSS to ChampaTSS (52 km), Champa TSS to Gevra RD TSS (45km), Champa TSS to Bilaspur Bus Coupler (74km); Extension of 220 kV bay at Raigarh(PGCIL); LILO 3 Nos at Champa, Kharsia &Raigarh along with associated works inconnection with Direct Power Supply fromCentral Generating Agencies over South EastCentral Railway, Bilaspur, Chhattisgarh(India). (Rs. 245.95 crore)
Package-1: Design, Supply, Erection, Testingand Commissioning of 220 kV, 3-Phase D/Ctransmission line (7 km) from Bhatapara(PGCIL GSS ) to Bhatapara TSS, Bhatapara TSSto Bilaspur Bus Coupler(45 km), Bilaspur BusCoupler to Belghana TSS (55 km), Bilaspur BusCoupler to Bilaspur TSS (6 km), and BhataparaTSS to Urkura Bus Coupler(65 km); Extensionof 220 kV bay at Bhatapara (PGCIL); LILO 1No. at Bhatapara TSS and Bus Coupler 1 Noat Bilaspur along with associated works inconnection with Direct Power Supply fromCentral Generating Agencies over South EastCentral Railway, Bilaspur, Chhattisgarh(India). (Rs. 194.34 crore)
Package-3: Design, Supply, Erection, Testingand Commissioning of 220 kV, 3-Phase D/Ctransmission line (12 km) from Kumhari (PGCILGSS) to Bhilai TSS, Bhilai TSS to RajnandgaonTSS (55 km), Rajnandgaon TSS to Paniajob TSS(45 km), Bhilai TSS to Urkura Bus Coupler (35km) and Urkura Bus Coupler to Urkura TSS (5km); Extension of 220 kV bay at Kumhari
(PGCIL); LILO 2 Nos at Bhilai & Rajnandgaonand Bus Coupler 1 No at Urkura along withassociated works in connection with DirectPower Supply from Central GeneratingAgencies over South East Central Railway,Bilaspur, Chhattisgarh (India). (Rs.194.04crore)
Package-iii: Construction of Major Bridges &Road Under Bridges for electrified new BGRailway line (pkg-3) between Khategaon(incl) - Budni stations (chainage 110.000 to198.000 km) in Bhopal Division of West CentralRailway in Madhya Pradesh State, India. (Rs.175.19 crore)
Package-AAI Subway: Construction of AAISubway/Underpass across VIP Road fromAirport Operational Area to AAI ResidentialColony at NSCBI Airport, Kolkata passingbelow the Metro Ramp structure of NewGaria-Airport Metro Corridor, West Bengal.(Rs.154.21 crore)
Package 2: Provision of Automatic BlockSignaling System with dual MSDAC andalteration in existing EI/PI/Stations in thesection of Kaluparaghat (Excluding KAPGYard) - Golanthra over Khurda Road Divisionof East Coast Railway. (Rs. 77.24 crore)
Package 1: Provision of Automatic BlockSignaling System with dual MSDAC andalteration in existing EI/PI/Stations in thesection of Jakhapura-Nergundi & KhurdaRoad-Kaluparaghat (including KAPG yard)over Khurda Road Division of East CoastRailway. (Rs. 76.41 crore)
Mechanized Installation and linking of BGrailway track, P.way material supply, TrackBallast Supply, Mobile Flash Butt Welding ofjoints and all other associated P-way works(excluding supply of rails, PSC sleepers) insection between Bhanupali (Ch 0.00) toPaharpur (Ch 24.00) in connection withBhanupali-Bilaspur-Beri New Railway Line inDistrict Rupnagar of Punjab and Bilaspur ofHimachal Pradesh States, India. (Rs. 74.65crore)
Complete Interior Fit out works includuingFlooring, Wall and Ceiling Finishes,Partitioning, Civil, Furniture, Furnishing,Electrical, HVAC, MEP, Fire Fighting, IT andAudio-Visual Works etc. of RVNL office spaceat WTC Narouji Nagar, New Delhi throughSpecial Limited Tender. (Rs. 49.97 crore)
Design, Supply (except Galvanized SteelStructures and all type of Conductors-Feeder
Wire, AEC, BEC), Erection, Testing andCommissioning for upgradation of Electrictraction system from 1 x 25 kV to 2 x 25 kVtraction system under jurisdiction of Chaibasadepot of Rajkharsawan- Nayagarh-Bolanisection of Chakradharpur division of SouthEastern Railway to meet 3000 MT loadingtarget. (Rs. 39.12 crore)
Design, Supply (except Galvanized SteelStructures and all type of Conductors-FeederWire, AEC, BEC), Erection, Testing andCommissioning for upgradation of Electrictraction system from 1 x 25 kV to 2 x 25 kVtraction system under jurisdiction of Banspanidepot and Dongaposi Depot ofRajkharsawan- Nayagarh- Bolani section ofChakradharpur division of South EasternRailway to meet 3000 MT loading target.(Rs. 38.71 crore)
Providing Rockfall Barriers and SlopeProtection Works at different locations inconnection with Barkhera - Budni 3rd LineProject on Bhopal Division of West CentralRailway in Madhya Pradesh State, India.
(Rs. 40.13 crore)
Besides these Works Contract, FLS, DD&PMCand PMC contracts on nomination basis forRs. 32.99 crore have also been awardedduring 2024-25.
4. Project Planning & Development
As a part of the mandate of Rail Vikas NigamLimited (RVNL) to undertake projectdevelopment, mobilization of financialresources and to implement projectspertaining to strengthening of GoldenQuadrilateral and better connectivity tovarious ports, five Special Purpose Vehicles(SPVs) as Joint Ventures (JVs) have beencreated. RVNL has a minimum equityparticipation of 26 percent in each one ofthese SPVs.
Through these SPVs, RVNL has been able tomobilize a cumulative investment of Rs.10752.67 Cr. out of which Rs. 3873.11 Cr. isequity and Rs. 6879.56 Cr. is debt. RVNL itselfhas invested a total of Rs. 1520.65 Cr. as equityin these 5 SPVs, which is approximately 14.14%of their gross total investment (refer to tablebelow).
Name of SPV
Length Paid upEquity
RVNL's Equity
Partners' Equity
Initial
Debt
Subsequent
(Equity+
Debt)
In Kms
Crore
(Rs.)
%age
Kutch RailwayCompany Ltd*
821.00
410.50
50.00%
300.00
1284.41
1584.41
2405.41
Bharuch DahejRailway Company Ltd.
155.11
55.00
35.46%
100.11
64.54%
230.00
0.00
385.11
KrishnapatnamRailway Company Ltd.
113
625.00
311.00
49.76%
314.00
50.24%
1074.97
1699.97
Haridaspur ParadipRailway Company Ltd.
1300.00
390.00
30.00%
910.00
70.00%
1451.61
2751.61
Angul SukindaRailway Ltd.
104
972.00
354.15
36.44%
617.85
63.56%
1600.00
938.57
2538.57
3510.57
663
3873.11
1520.65
39.26%
2352.46
60.74%
4656.58
2222.98
6879.56
10752.67
*Note: The cost of GC was Rs. 550 Cr. Subsequently, the Doubling and Electrification works wereexecuted with a cost of Rs. 3153.70 Cr. (Doubling) & Rs. 755 Cr. (RE) respectively
Railway/Division/State
Western Railway/Ahmedabad/Gujarat
Project Type& Length
Gauge Conversion, 301 km
Year of Sanction
1988-89
Date of Transfer to RVNL
14.05.2003
Date of MoU
03.01.2004
Date of EOI
NA
Date of Incorporation
22.01.2004
Shareholders Agreement signed on
22.04.2004
Traffic Guarantee Agreement signed on
Not signed
Concession Agreement signed on
08.11.2005
Construction Agreement signed on
GC - 06.10.2005, DL-13.08.2018, RE - 09.02.2021
O&M Agreement signed on
21.08.2005
Original cost (Rs. Crore)
344.63
Project cost (Rs. Crore)
550.00
Equity Participants
Rail Vikas Nigam Limited 410.50 50.00%Deendayal Port Authority 213.46 26.00%Adani Ports & SEZ Limited 164.20 20.00%Govt. of Gujarat 32.84 4.00%Total (Rs. Crore) 821.00 100.00%
Bonus shares were issued in Nov-2011 amounting toRs. 50 Crore in the ratio of 1:4.
Commercial Operations Date (COD)
01.07.2006
Western Railway/Vadodara/Gujarat
Project Type & Length
Gauge Conversion, 63 Km
2005-06
22.03.2006
13.01.2005
27.02.2006
15.11.2006
12.01.2007
Traffic Guarantee Agreement
signed on
25.06.2008
01.07.2009
262.00
395.00
Rail Vikas Nigam Limited
Gujarat Maritime Board
17.86
11.51%
Gujarat Industrial Development Corporation
Adani Petronet (Dahej) Port Private Limited
17.33
11.17%
Gujarat Narmada Valley Fertilizer Company 13.53
8.72%
Hindalco Industries Limited
13.53
Dahej SEZ Limited
6.45%
Jindal Rail Infrastructure Limited
Total (Rs. Crore)
100.0%
08.03.2012
South Central/Vijayawada/Andhra Pradesh
New Line, 113.12 Km
2006-07
22.11.2005
11.10.2006
13.10.2006, Participation Agreement- I on 23.02.2008,Participation Agreement -II on 12.10.2020.
Traffic Guarantee Agreementsigned on
23.11.2007
29.09.2011
06.01.2012 08.11.2021 (Revised)
732.81
Estimated Project cost (Rs. Crore)
2831.00
Rail Vikas Nigam Limited 311.00
Sagarmala Development Co. Ltd 125.00
20.00%
Adani Krishnapatnam Port Co Ltd 81.00
12.96%
National Mineral Development Co. Ltd 40.00
6.40%
Govt. of Andhra Pradesh 35.00
5.60%
Bramhani Industries Ltd 33.00
5.28%
Total (Rs. Crore) 625.00
a. Venkatachalem - Nidiguntapalem - 01.10.2008
b. Nidiguntapalem - Krishnapatnam - 28.02.2009
c. Doubling of 21 km line from VKT to KAPT - 02.03.2014
d. The complete connectivity was commissioned in June 2019
East Coast Railway/Khurda Road/Odisha
New Line, 82 Km
1996-97
24.02.2005
21.01.2006
25.09.2006
04.04.2008
20.12.2007
11.08.2009
24.10.2021
301.64
2397.00
Sagarmala Development Company Ltd.
336.79
25.91%
Govt. of Odisha
237.79
18.29%
Paradip Port Trust
138.52
10.66%
Orissa Mining Corporation
110.00
8.46%
Essel Mining & Industries Ltd
30.00
2.31%
Rungta Mines Ltd
MSPL Ltd
15.00
1.15%
Jindal Steel Power Limited
5.00
0.38%
Steel Authority of India Ltd.
Odisha Industrial Infrastructure
1.90
0.15%
Development Corporation (IDCO)
1300.0
30.07.2020
New Line, 104.242 Km with Y-connection
1997-98
22.02.2006
19.11.2008
17.06.2008
20.02.2009
27.05.2009
14.05.2010
24.04.2015
391.00
2913.00
354,15
239.47
24.64%
CONCOR
208.00
21.40%
Odisha Mining Corporation
106.18
10.92%
60.00
6.17%
4.20
0.43%
01.03.2023
4.2 Rail Vikas Nigam limited (RVNL) has started participating in Metro, Highways and other Infrastructuresectors through competitive bidding. Therefore, New SPVs in other sector have been incorporatedto undertake such projects.
S. Name of SPVNo.
Date ofIn
Paid upEquity
Corporation
Crore (Rs.)
Crore (Rs.) %age
Shimla Bypass KaithlighatShakral Pvt. Ltd.
05.08.2022
110.10
55.05
50%
Chennai MMLP Pvt. Ltd.
06.10.2022
0.05
0.013
26%
0.037
74%
Bengaluru MMLP Pvt. Ltd.
10.01.2023
0.0082
16.33%
0.0418
83.67%
Indore MMLP Pvt. Ltd.
17.05.2023
0.011
22.01%
0.039
77.99%
Chatra Expressways Pvt. Ltd.
24.04.2023
0.01
0.0049
49%
0.0051
51%
Kyrgyzindustry-RVNL CJSC
07.12.2022
84,00,000
soms
42,00,000
Kinet Railway Solutions Ltd.
19.04.2023
41.76
10.44
25%
31.32
75%
JGPL-RVNL EPC Private Ltd.
15.01.2024
The Government of India had entrusted to the Authority (NHAI) the development, maintenanceand management of Greenfield alignment of National Highway No 5-including the section fromkm 128.835 to km 146.300 (approx. 17.465 km). The Authority had resolved to Construction of 4Laning of NH-5 from Kaithlighat to Shakral Village for Design Length 17.465 km in the State ofHimachal Pradesh by Four-Laning thereof on design, build, operate and transfer (the "DBOT Annuity"or "Hybrid Annuity") basis, which shall be partly financed by the Concessionaire who shall recoverits investment and costs through payments to be made by the Authority.
The Consortium has been promoted and incorporated the Concessionaire as a limited liabilitycompany under the Companies Act 2013 named Shimla Bypass Kaithlighat Shakral Pvt. Ltd. by RailVikas Nigam Ltd. and M/s S P Singla Constructions Pvt. Ltd as its lead members for the execution ofthe project.
Brief of the Project:
Location and State
4-Lane Bypass, Package-I, Kaithlighat to Shakral, Shimla, Himachal Pradesh
Hybrid Annuity Mode & 17.465 km
15.05.2022
Project cost
1) Bid Project Cost (BPC) - Rs. 1844.77 Crore excluding GST
2) First Year O&M Bid - Rs. 2.77 Crore excluding GST
Adjusted Bid Price - Rs. 1637.96 Crore (NPV of BPC and First Year O&M)
Equity Participants and
SPSCPL- 50%
their % share
RVNL- 50%
Anticipated Commercial After the end of Construction period tentatively 20.04.2026Operations Date (COD)
• Multi Modal Logistics Park is an integrated facility within which all activities relating to logistics andthe distribution of goods, both for national and international transit can be carried out acrossmultiple modes of transport. MMLPs also benefit from economies of scale, by creating sharedinfrastructure and due to availability of more options for selection of competitive and reliablelogistics providers
• MMLP at Chennai is being developed at Mappedu (Thiruvallur district) in 184.27 Acres of Area. Thesite is strategically located, at approximately 52 kms from Chennai Port, 80 kms from Ennore Portand 87 Kms from Kattupalli Port. Chennai Airport is located at approximately 44 kms from the site.
• The estimated total project cost is INR 1424 Cr. The Project is proposed to be developed in PPPmode where in a Developer will be appointed with a Concession Period of 45 years for developingand operating the MMLP with an estimated cost of INR 783 Cr.
• SFC appraisal was held on 09.05.2022 and subsequently MoRTH has approved the project on06.06.2022. Hon'ble Prime Minister also laid the Foundation Stone of the project on 26.05.2022.
• A Govt. SPV formed amongst National Highways Logistics Management Limited, Rail Vikas NigamLimited, Chennai Port Authority & Tamil Nadu Industrial Development Corporation will provideland for the MMLP, external road and rail connectivity, power supply etc.,
Village Mappedu (Hussein Nagaram) in Thirivallur dist., Tamil Nadu
Project Type
Development of Multi Modal Logistics Park Mappedu Chennai in TamilNadu along with external Road, Rail and other connectivity
12-10-2021 among ChPA, NHLML & TIDCO Supplementary MOU on dated24-05-2023 with inclusion of RVNL
06/10/2022
Rs. 1423.50 Cr.(Concessionaire investment Rs. 782.58 Cr. + Authorityinvestment - including cost of land Rs.640.92 Cr.)
NHLML- 40.18%
Ch PA- 26.02 %RVNL- 26.00 %TIDCO- 07.80%
Anticipated CommercialOperations Date (COD)
For Phase 1- 02 years from the appointed Date. October 2025 (Scheduled)
U Connecting Hubs
Distance (km) !
Chennai Port
52
Ennore Port
80
Kattupalli Port
87
Chennai Int. Airport
Bengaluru's Multi Modal Logistics Park (MMLP) awarded and set to span across 400 acres in Bengalururural district.
MMLP is a key policy initiative of the Government to improve the country's freight logistics sectorby lowering overall freight costs and time, cutting warehousing costs, reducing vehicular pollutionand congestion, improving the tracking and traceability of consignments through infrastructural,procedural, and information technology interventions.
MMLP at Bengaluru is being developed in an area of 400 acres at Muddelinganahalli in Bengalururural district in Karnataka. The site is strategically located, adjacent to the upcoming KIADB industrialarea on East side, abutting the NH 648, Dabbaspet to Hosur as well as Satellite Town Ring Road onNorth side and Bengaluru - Hubli - Mumbai rail line on South side. The site is 58 Kms from BengaluruInternational Airport and 48 Kms from Bengaluru city railway station.
A government SPV formed between National Highways Logistics Management Limited (NHLML),Rail Vikas Nigam Limited (RVNL) and Karnataka Industrial Area Development Board (KIADB) willprovide land for the MMLP, external rail, road connectivity as well as water and power supply. TheMMLP is being provided with 4 lane access from four lane Dabbaspet - Hosur, NH 648 and railsiding of length 4.5 km from Dodbele Railway station on Bengaluru - Hubli- Mumbai rail line.
The MMLP will be developed in three phases. The Phase-I is expected to be completed in two years.MMLP will cater to about 30 million metric tonnes (MMT) cargo in the horizon period of 45 years andwill give huge boost to the industrial zones in the catchment region such as Bengaluru and Tumkur.It will create lot of employment opportunities and bring in economic development in the region.
Bengaluru Karnataka
Development of Multi Modal Logistics Park Bengaluru in Karnataka alongwith external Road, Rail and other connectivity
01.09.2022
Rs. 1769.9 Crore (Concessionaire investment Rs. 935.90 Cr + Authorityinvestment Rs. 834 Cr, including land cost of Rs. 540 Cr.
Equity Participants andtheir % share
NHLML- 51.29%KIADB - 32.38%RVNL- 16.33%
For Phase 1- 02 years from the Appointed Date (AD). ScheduledAnticipated Date: 29.02.2024
Indore MMLP Pvt. Ltd.has been incorporated for "Development of Multi Modal Logistics Park atIndore (Area 255.17 Acre)".
Near Pithampur Industrial area, Dist. Dhar, Madhya Pradesh
Development of Multi Modal Logistics Park Indore. Area 255.17 Acres
26.12.2022
Rs. 1111 Cr. (Auth. investment 353 Cr. + Concessionaire InvestmentRs. 758 Cr.)
MPIDC (50% of MMLP Land Cost)- 25.16%
RVNL (Rail Development, limited to 26% of total equity contribution)- 22.01%NHLML (Road Development and LA Cost, 50% of MMLP Land Cost, railconnectivity LA cost and Cost towards Power & Water Supply and othercharges) -52.83%
Anticipated Commercial 19.12.2025Operations Date (COD)
MMLP - Location at Kheda/Jamodi/Akolia
Chatra Expressways Pvt. Ltd. has been incorporated for "Work of construction of 6-lane greenfieldVaransi-Ranchi-Kolkata Highway from Sonepurbigha village to the junction with NH 22 (ChatraBypass) near Chatra from km 184.700 to km 222.000.
Chandauli, Uttar Pradesh to Bangam, Kolkata
Construction of 6-lane Greenfield Varanasi-Ranchi-Kolkata Highway fromSonepurbigha village to junction with NH-22 (Chatra Bypass) near Chatrafrom km 184.700 to km 222.000 under Bharatmala Pariyojana in the Stateof Jharkhand on Hybrid Annuity Mode (Package 8). The length of theproject is 37.300 kms.
Rs. 1458 Cr.
Equity Participantsand their % share
Tracks & Towers Infratech (P) Ltd.- 51%Rail Vikas Nigam Limited- 49%
Anticipated Commercial 730 days from Appointed Date (Appointed Date yet to be declared byOperations Date (COD) NHAI)
A Closed Joint Stock Company "Kyrgyzindustry-RVNL" has been incorporated in December, 2022.RVNL is having equity investment of 4200000 soms (being 50% of total equity). A DPR has beenprepared for Balykechy & Kara-Kecheline line of total cost of USD 2.3 billion.
Kyrgyz Republic, Bishkek City, 106 Chui Avenue
The JV company shall undertake Infrastructure development i.e.,Construction of Railroads in and across Kyrgyz Republic, includingConstruction of Highways and Freeways, construction of bridges andtunnels and other activities not inconsistent with the laws of the KyrgyzRepublic and consistent with the statutory objectives.
30.05.2022
Kyrgyzindustry Open Joint Stock Company-50%Rail Vikas Nigam Limited-50%
RVNL, in collaboration with its consortium partners, has signed the prestigious Manufacturing cumMaintenance Agreement of Vande Bharat Trainsets including upgradation of the GovernmentManufacturing Units & Trainset Depots. This project is being executed through a Special PurposeVehicle (SPV) named Kinet Railway Solutions Limited (KRSL), jointly owned by RVNL and its consortiumpartners namely JCS Meterowagonmash (MWM), JSC Locomotive Electronic Systems (LES), andRail Vikas Nigam Limited (RVNL), MWM holding a dominant share of 70%, LES contributing 5%, andRVNL owning remaining 25%. Acting as the Technology Partner, KRSL is spear heading theimplementation of this visionary initiative.
KRSL has been entrusted with the manufacturing of 120 Vande Bharat Trainsets at theManufacturing Unit located in Latur, Maharashtra.
A planned maintenance regime has been devised, earmarking three designated depots -Bijwasan, Jodhpur, and Thanisandra - for the servicing and upkeep of these cutting-edgetrainsets, ensuring their operational excellence for a period spanning 35 years.
Comprehensive infrastructural planning, including the provision of state-of-the-art facilitiesas well as machinery, has been undertaken to equip the designated depots, ensuring seamlessoperations and maintenance activities.
The project timeline entails the delivery of the first prototype of the Vande Bharat Trainset tothe Indian Railways by September 2025, followed by second prototype by November 2025.Regular deliveries follow marking a significant milestone in the nation's pursuit of advancedrailway infrastructure.
New Delhi, India
"Manufacturing cum Maintenance of Vande Bharat Trainsets includingupgradation of the Government Manufacturing Units & Trainset Depots"
- 200 Vande Bharat Train sets of Sleeper version, each of 16 cars.
- Supply and undertake comprehensive maintenance thereof for a
period of 35 years.
The L1 selected bidder would have to manufacture/assemble total120 Trainsets at Railway's Marathwada Rail Coach Factory (MRCF)/Latur.
The L2 selected bidder would have to manufacture/assemble total80 Trainsets at Railway's ICF/Chennai.
14.11.2022
The total quantity is 120 Trainsets and cost per set is Rs. 120 crores.(as per LOA)
RVNL- 25%
Joint Stock Company Metrowagonmash- 70%
Joint Stock Company Locomotive Electronic Systems- 5%
82 Months (Time period by which the order(s)/contract(s) is to be executed- As per LOA)
A 626, 6th Floor, DLF Tower A, Jasola, Sarita Vihar, South Delhi - 110076
Grid Connected Solar PV Project along with Battery Energy StorageSystem (250 MW - Solar and 63 MW BESS)
~USD 154 Million
RVNL- 49%
Jakson Green Private Limited- 51%
Anticipated Commercial February 2025Operations Date (COD)
As on Date of Report, RVNL has incorporatedfollowing wholly owned SubsidiaryCompanies in India & abroad:
1. HSRC Infra Servies Ltd. -Incorporated on25.07.2012 in Delhi
2. Masakani Paradeep Road Vikas Ltd.-Incorporated on 21.08.2023 in Orissa
3. RVNL Infra South Africa Incorporated on
15.01.2024 in South Africa
4. RVNL Infra Middle East- Incorporated on
04.04.2024 in Sultanate of Oman
5. RVNL Middle East Contracting L.L.C. (Dubai)-Incorporated on 26.06.2024 in Dubai
6. Rail Vikas Nigam LLC- Incorporated on
01.08.2024 in Uzbekistan
7. Rail Vikas Nigam Limited Company (OnePerson)- Incorporated on 18.10.2024 inKingdom of Saudi Arabia.
8. Sabbavaram Sheelanagar RoadDevelopment Ltd.- Incorporated on
15.05.2025 in Andhra Pradesh
5. Personnel Development
Hiring of talented and experiencedmanpower, developing, motivating andretaining them have been the principal areasof HR for achieving the corporate objectives.
The primary focus of the organisation hasbeen to have not only a lean and thin cadreof highly motivated, skilled and experiencedmanpower but also to retain these scarcelyavailable resources by creating a conducivework environment.
HR policies are meticulously framed takinginto account the short-term and long-termmanpower requirements of the organisation.As RVNL is mandated to execute Railwayprojects for and on behalf of Ministry ofRailways, persons with requisite technicalexpertise and domain knowledge of RailwaySystems and Railway construction are requiredfor smooth and timely completion of railprojects assigned to RVNL. The manpower islargely met by sourcing employees fromRailways and other Government Departmentson deputation basis. RVNL has also a regularcadre of its own created by absorbing willingemployees from Railways, other Govt.Departments and PSUs. As on 31.03.2025, theon-roll strength of the company stood at 213regular employees and 125 deputationists.Apart from absorbing Railway employees,Recruitment are being made on contract basisfor various projects taken on Bidding apartfrom regular recruitment.
RVNL has attractive and employee- friendlypolicies to boost the morale and motivate
the employees to perform to the best of theirabilities. The perks and perquisites being paidto the employees are reviewed periodicallyto enhance the efficiency.
Skill development of the employees has beengiven special attention through in-house andcustomised training programmes to theemployees at different levels not only relevantto their working area but also to enhancetheir overall capabilities so that theemployees are able to adapt to the changingtechnology and customer needs anddischarge their roles as a strategic businesspartner contributing in the growth of theorganisation.
As a motivation to the employees, RVNLrecognises the services of meritoriousemployees through individual/group Awardsand by presenting shields and cash awardsevery year on the Annual Day function.
Welfare Programmes:
In line with the guidelines of the Government,the RVNL conducted many welfareprogramme such as arranging medicalcamps for Regular, Deputationists,Housekeeping & Outsource employees andtheir families. Women day celebration wasorganised on 07.03.2025 for all the womenemployees of the organisation.
Cordial and harmonious Industrial relationshave been maintained through out the year.All efforts were made to keep the employeesand their families safe during the Covidpandemic by complying with the safetyprotocols and guidelines.
5.2 Disclosure under the Sexual Harassment ofWomen at Workplace (Prevention, Prohibition& Redressal) Act, 2013.
The RVNL Conduct and Discipline Rules arein line with the requirements of the SexualHarassment of Women at the Workplace(Prevention, Prohibition & Redressal) Act,2013. An Internal Complaints Committeecalled “Vishaka Committee” has been set upin RVNL to redress complaints receivedregarding sexual harassment. All employeesare covered under this policy. The followingis a summary of sexual harassmentcomplaints received and disposed of fduringthe calendar year:-
i) No. of complaints received: Nil
ii) No. of complaints disposed of: Nil
The provisions of the Right to Information Actare followed diligently in letter and spirit andtimely responses are given to all queries. TheCompany has nominated AppellateAuthority, Chief Public Information Officer andAsstt. Public Information Officer at theCorporate Office and Asstt. PublicInformation Officer for each PIU. During theyear 2024-25, 250 Applications were receivedand disposed off.
The company has been making concertedefforts to implement the directives of theGovernment of India on use of Rajbhasha(Official Language). The RajbhashaDepartment of the Company has a Part-timeMukhya Rajbhasha Adhikari and Sr. DGM(Rajbhasha) cum Up-Mukhya RajbhashaAdhikari. All the computers in the CorporateOffice have been provided with Unicodecompliant software and fonts to facilitateaccess to common templates in Devnagari.To encourage use of Rajbhasha, total 10officials who use Rajbhasha in Hindi draftingnotes and letters were identified from all thedepartments and given Late Shankar DayalSingh Smriti Puraskar amounting to Rs. 3,000/- each. A competition on Hindi essay writing,Hindi noting and drafting, Hindi Shabd Gyanand Quiz was organized on the occasion ofHindi Pakhwara in the month of September,2024. Cash awards of Rs. 64,100 weredistributed to 23 successful participants. TheCompany has also set up a reading room-cum-library in the Corporate Office with agood collection of books, newspapers andperiodicals in Hindi. During 2024-25, 4meetings of the Rajbhasha ImplementationCommittee of RVNL were held andpromotion of Rajbhasha was discussed andreviewed. During Financial Year 2024-25,Parliamentary Committee (On OfficialLanguage) carried out inspections of Ranchi,Bhubaneswar and Chennai Units andCommittee has expressed satisfaction. HindiChitra Varnan Pratiyogita was organized on
10.02.2025 on the directives of Delhi NagarRajbhasha Karyanvayan Samiti, DelhiUpkram-2, in which total 26 Officialsparticipated, out of which 5 were awardedwith cash award amounting to Rs. 7,800.During Financial Year 2024-25, Nagar OfficialLanguage Implementation Committee,Upkram-2 has provided Rajbhasha Shield toRVNL for organizing Hindi Prashn ManchPratiyogita for member offices of Nagar OLIC
Upkram-2.
During the year 2024-25, no presidentialdirective was issued.
6. Vigilance
Vigilance Department is headed by ChiefVigilance Officer (CVO). RVNL Vigilancefunctions with a dominant focus onpreventive approach towards strengtheningtransparency in the systems, work proceduresand accountability. Besides examining theallegations in the complaints received fromvarious fora, it also carries out preventivechecks and inspections. The findings of theseinvestigations/inspections are
communicated to the Management forsuitable action including systemimprovements, wherever required. Thecompliance of corrective actions suggestedagainst deficiencies/lapses noticed duringthe inspections/preventive checks are alsoensured.
During the FY2024-25, focus was made tofinalize/conclude the pending CVC/CTE/Vigilance cases by vigorously pursuing theconcerned authorities/RVNL field units fortheir comments/action taken. During theperiod, RVNL Vigilance also assisted in theIntensive Examination of Works by CTE/CVCconducted for two (02) works pertaining toJhansi PIU and Metro/Kolkata PIU. Moreover,observations made during earlier CTE/CTEType inspections were followed up and replieson paras pertaining to various CTEinspections were sent to CTE/CVC.
During the period, six (06) CTE Type checksand six (06) preventive checks wereconducted by RVNL(Vigilance). Besides,comments against pending paras of CTEchecks conducted in earlier years were alsosent to the Commission and many paras alsogot closed from CVC.
The complaints received by Vigilance fromtime to time were dealt with as perprocedure prescribed by CVC & DoPT. Duringthe FY 2024-25, out of (46) complaints (otherthan PIDPI), all complaints were promptlydisposed by RVNL vigilance. Three Systemimprovements were suggusted which wereimplemented by RVNL Management.
During the FY 2024-25 approx. 505 cases ofvigilance status of officers/employees wereprocessed by RVNL Vigilance as required byHR/RVNL, Railway Board Vigilance, ZonalRailways Vigilance etc. All Vigilance status/clearance cases were processed invariablythrough e-office for prompt disposal.
The status of various matters namelyinspections, complaints, disciplinary casesand miscellaneous matters was regularlyapprised to CVC/Railway Board throughperiodic quarterly and Annual Reports. Thequarterly progress report of physical progressof different works being executed by RVNLwas duly sent to CTEO (Office of ChiefTechnical Examiner under Central VigilanceCommission) for each quarter.
v In a move towards inculcating the true spiritof participative vigilance, the CentralVigilance Commission had issued instructionsdetailing a three- month campaign period(16th August, 2024 (Friday) till 15th November,2024 (Friday). As per CVC's advice, in the 03-months long campaign, following preventivevigilance measures were taken up as focusAreas by all the Ministries/Departments andOrganizations:
a. Capacity Building programs
b. Identification and implementation ofSystemic Improvement measures
c. Up-dation of Circulars/Guidelines/Manuals
d. Disposal of complaints received before30.06.24
e. Dynamic Digital Presence
7. Memorandum of Understanding
The Company secured a rating of “Excellent”by Department of Public Enterprises for theyear 2023-24 on the basis of the achievementof the committed targets fixed in theMemorandum of Understanding signedbetween RVNL and Ministry of Railways. Thisis the fourteenth consecutive year for whichthe Company has been rated as “Excellent”.
During FY 2024-25, MoU includes some of thecompliance parameters and theircompliance status are as follows:
Certificate on Compliance of AssetMonetization Milestones for thefinancial year 2024-25.
Complied
Company has not received any target from Niti Aayog/Ministryof railways (MoR) for the financial year 2024-25
Certificate on Compliance ofprovisions of the Companies Act,2013, SEBI (LODR) Regulations, 2015and any other relevant acts, rules andregulations under which it is regulated(to the extent the compliances arewithin the ambit of rVnL) for thefinancial year 2024-25.
(to the extent the compliances are within the ambit of RVNL)
Certificate on Compliance of DPEguidelines issued from time to time forCSR Expenditure by CPSEs for thefinancial year 2024-25
(Refer CSR Report)
Guidelines on Steps and initiativetaken for Health & SafetyImprovement of Human Resources inCPSEs for the financial year 2024-25.
RVNL organized various Health camps and awareness programas a part of its commitment to public health and diseaseprevention. These initiatives included General Health camps,Intensified TB Elimination Campaign, Health Capm on worldcancer day, Women Health awareness program on InternationalWomen's day, TB screening camp on World TB day
Acceptance/Rejection of invoices ofGoods & Services of MSME vendorsthrough TReDs.
Procurement of goods or servicesthrough Micro and Small Enterprises(MSEs) as % of total procurement ofgoods and services
Rail Vikas Nigam Limited has complied with the PublicProcurement Policy for Micro and Small Enterprises (MSEs) Order,2012, and procured goods and services from MSEs (includingMSEs owned by SC/ST and Women entrepreneurs) to the tuneof Rs. 19.41 crores (37.81% of the total procurement) againstthe target of Rs.12.83 crores.
Procurement from GeM Portal as % oftotal procurement
Rail Vikas Nigam Limited has complied with the Policy forprocurement of goods and services from GeM Portal for thefinancial year 2024-25 and goods and services amounting toRs.33.66 Cr is procured from GeM Portal against target ofRs.19.36 Cr during F.Y. 2024-25.
Procurement of goods or servicesthrough SC/ST Micro and SmallEnterprises (MSEs) as % of totalprocurement of goods and services-4%
Rail Vikas Nigam Limited has complied with the PublicProcurement Policy for SC/ST Vendors for the financial year 2024¬25 and procured goods and services amounting to Rs.2.28crores from SC/ST Vendors i.e. 4.45% of total procurement targetinstead of 4% of total procurement during F.Y. 2024-25.
Procurement of goods or servicesthrough Women Micro and SmallEnterprises (MSEs) as % of totalprocurement of goods and services
Rail Vikas Nigam Limited has complied with the PublicProcurement Policy for Women Entrepreneur for the financialyear 2024-25 and procured goods and services amounting toRs.3.22 crores from women vendors i.e. 6.27% of totalprocurement target against 3% of total procurement of goodsand services during F.Y. 2024-25.
8. Particulars relating to Conservation ofEnergy, Technology Absorption andForeign Exchange Earnings and Outgoetc.
Absorption
RVNL is conscious of the limited nature ofconventional sources and the importance ofusing our energy resources wisely. TheCompany has been consistently layingemphasis on utilizing energy efficientequipment in its office premises and in variousprojects so as to minimally effect on theecology and environment. Initiatives takento create awareness about conservation ofenergy among employees have resulted in asteady reduction in energy consumption atCorporate Office. Various environmentfriendly technologies have been adopted inthe Corporate Office building. Solar panelsare installed at all Railway Stations and levelcrossings. LED lighting system also installedand wherever feasible, automatic censorbased lightings are installed.
The Foreign Exchange Outgo during the yearin terms of actual outflows as compared toprevious year is mentioned below:
(Rs. In crores)
2024-25
Import of Material
100.88
Import of Capital Goods
85.46
Foreign Exchange on
1.32
1.11
Foreign Travel of
Company's officials
Business Promotion
3.55
Purchase of tender
Bank Charges
0.04
0.09
4.91
187.54
RVNL has a formal Risk Management Policyduly approved by the Board of Directors. ThePolicy aims to review the exposure of RVNLto various risks and the mitigation measuresto be taken periodically. It also strives toincrease awareness among its employees andother stakeholders about possible risks andmeasures to control the same.
The Company has a Risk ManagementCommittee under the Chairmanship of
Director (Operation) with all FunctionalDirectors as members and Executive Directorsas special invitees.
During the quarterly review, the committeedeliberated on the key challenges/criticalarea of potential risk to the company andthe following challenges/risks were identified:
a) Release of Funds from Himachal PradeshGovt, Andhra Pradesh Government,Telangana & Maharashtra Government.
b) Improving website of RVNL fordissemination of information.
c) Protecting the website and relatedfunctions for Cyber Frauds.
d) Motivating the employees for newchallenges e.g overseas projects.
e) Increasing Social Media in presence ofRVNL & the number of followers hasbeen increased during 2024-2025
Following initiatives have been taken basedon the suggestions made by the RiskManagement Committee to overcome theabove challenges on pilot basis:
a) The matter is being continuously pursuedwith senior officials of respective StateGovernments. During the FY, release ofRs. 7.8 Cr. could be achieved.
b) A new website of RVNL has already beenlaunched and also RVNL profile hasbeen made on WIKIPEDIA.
entails:
The Framework document fordealing with cyber-related incidents.
It has the details of persons to becontacted for a particular failure& a list of IT assets which could helpwith separation of infectedinfrastructure.
It describes the different types ofCyber crises, their possible targets& associated impacts, as well asthe actions & responsibilities ofstakeholders involved.
Cyber incident responsecoordination among Ministries/Departments of the CentralGovernment, its agencies & criticalinformation infrastructureorganizations to deal with cybercrisis situations.
CCMP is periodically reviewed &Security audit is also conductedregularly
10. Corporate Social Responsibility (CSR)
The key philosophy of CSR, as enshrined in thepolicy, is to meet the following broadobjectives:
a) Implementation in project/programmemode
b) Focus on periphery of project areas ofRVNL
c) Thrust areas of education andhealthcare
d) Inclusive growth of society withemphasis on development of weakersections of society and in the backwarddistricts of the country.
The Company has constituted CorporateSocial Responsibility Committee (CSR) in linewith the requirements of the Companies Act,2013 and DPE Guidelines. The details withrespects to composition, CSR Policy and CSRactivities undertaken by the Company duringFY 2024-25 are placed as Annexure C to thisreport.
11. Compliance of provisions ofCompanies Act, 2013, SEBI (LODR)Regulations, 2015 and SecretarialStandards issued by ICSI
All the provisions of the Companies Act, 2013and the Rules made thereunder, SecretarialStandards issued by ICSI and SEBI (LODR)Regulations, 2015 to the extent possible andapplicable to the Company as well as allrelevant notifications thereon issued by theGovernment of India, are being strictlycomplied with.
12. Compliance of DPE Guidelines andPolicies
All the guidelines and policies includingguidelines having financial implicationsissued by Department of Public Enterprisesfrom time to time are duly complied with bythe Company.
13. Compliance of the Public ProcurementPolicy for Micro and Small Enterprises(MSEs) Order, 2012
The Government of India has notified PublicProcurement policy for Micro and SmallEnterprises (MSEs) Order, 2012 with effect from1st April, 2012. As the mandate of the PublicProcurement Policy for Micro and SmallEnterprises (MSEs) Order 2012, every CentralMinistries/PSUs is required to set an annualtarget of minimum 25% procurement ofgoods & services from MSE Sector. Out of Totalannual procurement, a sub target of 4% &3% should be from MSEs owned by SC/ST andWomen entrepreneurs respectively.
Rail Vikas Nigam Limited (RVNL) has takenseveral steps for effective implementation ofMSE Policy. The benefits of waiver of cost oftender documents and deposit of earnestmoney, prescribed under the policy, areincorporated in the tenders for storesprocurement and obtaining services etc.
Mrs Anupam Ban, Director (Personnel) isworking as Nodal Officer and a GrievanceOfficer has been nominated for seamlessimplementation of the MSE policy in RVNL.Contact details of these officers areuploaded on RVNL website.
Annual Procurement Plan for purchase fromMSEs during the year 2024-25 was madeavailable on RVNL website for informationof MSEs and to help them participate inprocurement of goods and services.
In the year 2024-25, RVNL procured goods andservices amounting to a total of Rs. 51.33crores. Out of this, the total value of goodsand services purchased from MSEs (IncludingMSEs owned by SC/ST and Womenentrepreneurs) was to the tune Rs. 19.41 croresi.e. 37.81% of the total procurement. Thus,RVNL has fully complied with the PublicProcurement Policy for Micro and SmallEnterprises (MSEs) Order, 2012.
As desired, the expenditure incurred by RVNLon under mentioned head of accounts forthe period from 01.04.2024 to 31.03.2025 isgiven below:
GL Code
Expenditure
(Cr.)
MSME
% ofMSE
Vehicle Hiring
5206050004
5.02
2.29
45.53%
Photocopy Exp./Printing & Stationary
5206110002/5206110003
2.51
0.67
26.85%
Outsourcing Staff
5206100005/5206120003
14.68
2.94
20.05%
Housekeeping /Security Service
5206170003/5206170004
16.01
10.25
64.02%
Office Equipment
1101010001
2.33
1.52%
Furniture and Fixtures
1101020001
1.02
9.03%
EDP Assets
1101030001
1.92
0.16
8.48%
14. Research and Development
RVNL is utilizing a number of IT initiatives inorder to automate the business processes ofthe organisation across employee services,office procedures, and project managementand vendor billings. Among the latest systemsimplemented, below are noteworthyaccomplishments:
RVNL is embarking on adapting DataAnalytics and Artificial Intelligence technologymaking all our processes centralised, digitisedand automated.
RVNL upgraded the data centre and shiftedto RailTel. With this now our systems arerunning on latest hardware.
RVNL, being a Navratna Public SectorEnterprise, ensures that as per InformationTechnology Act, 2000, Your Company hasalways been at the forefront in the adoptionof new technology solutions for the continualimprovement in its business processes. With avision to be a digitally empoweredorganization for operational excellence andstakeholder value creation, it has adoptedseveral path-breaking technologies in itstechnology stack. Various IT projects that arein pipeline for implementation are Upgradingour SAP systems from ECC 6 to S4/HANA,Implementing ISO 27001/2023 which is aninternationally recognised standard forinformation security management systems etc.
15. Directors' Responsibility Statement
Pursuant to Section 134(5) of the CompaniesAct, 2013, the Directors confirm that -
a) In the preparation of the annual accounts,
the applicable accounting standards havebeen followed along with proper explanationrelating to material departures;
b) The Directors have selected such accountingpolicies and applied them consistently andmade judgments and estimates that arereasonable and prudent so as to give a trueand fair view of the state of affairs of theCompany at the end of the financial year andof the profit of the Company for that period;
c) The Directors have taken proper andsufficient care for the maintenance ofadequate accounting records inaccordance with the provisions of this Actfor safeguarding the assets of the Companyand for preventing and detecting fraud andother irregularities;
d) The Directors have prepared the annualaccounts on a going concern basis.
e) The Directors have laid down internal financialcontrols to be followed by the Company andthat such internal financial controls areadequate and were operating effectively.
f) The Directors have devised proper systems toensure compliance with the provisions of allapplicable laws and that such systems wereadequate and operating effectively.
16. Directors and Key Managerial Personnel
RVNL being a Government Company, theappointment of directors on its Board aredone by the Govt. of India throughAdministrative Ministry i.e. Ministry of Railways,from time to time.
As on date of this report, the strength of theBoard of the Company comprises of Eight (8)Directors, out of which five (5) are whole-timeDirectors (including Chairman and Managing
Director), two (2) Government NomineeDirector from Administrative Ministry i.e.,Ministry of Railways (MoR) as (Part-time)(official) Directors and One (1) IndependentDirector. Position of six(6) IndependentDirectors (including one-woman IndependentDirector) is vacant. However, the compositionof the Board of Directors was not in conformitywith the provisions of the Companies Act,2013, SEBI (LODR) Regulations,2015 and DPEGuidelines on Corporate Governance, due toabsence of requisite number of IndependentDirectors including one Woman IndependentDirector on its Board.
The Company has been requesting Ministryof Railways (MoR), Government of India toappoint requisite number of Independentdirectors (including woman IndependentDirector) to ensure the compliance to theprovisions of SEBI (LODR) Regulations, 2015 andDPE Guidelines on Corporate Governance.Except the appointment of IndependentDirectors (including woman IndependentDirector), the composition of the Board is incompliance with Regulation 17 of SEBI (LODR)Regulations, 2015.
The following Directors held office during the year and till the date of this report-
Name & DIN of Directors
Designation
Date of Appointment/Cessation
Whole Time Directors/Functional Directors
Mr. Pradeep Gaur
(DIN:07243986)
Chairman and Managing Director
from 01.09.2018 onwards
Mr. Vinay Singh
(DIN:03324677)
Director (Projects)
From 01.08.2019upto 18.12.2024
Mr. Rajesh Prasad
(DIN:08585975)
Director (Operations)
From 03.03.2020 upto30.09.2024
Mr. Sanjeeb Kumar
(DIN:03383641)
Director (Finance) & CFO
from 06.05.2020 upto31.05.2025
Mrs. Anupam Ban
(DIN:07797026)
Director (Personnel)
From 09.02.2023 onwards
Mr. Sandeep Jain
(DIN:09435375)
Director (Operations)Additional Charge
From 01.10.2024 upto25.11.2024
Mr. Mritunjay Pratap Singh
(DIN:08165734)
from 26.11.2024 onwards
Director (Projects)Additional Charge
From 06.02.2025 onwards
Mr. Abhishek Kumar
(DIN:10644411)
Director (Finance)Additional Charge
From 05.06.2025 onwards
Government Nominee Directors/Part time Official Directors
Mr. Dhananjaya Singh
(DIN:08955500)
Govt. Nominee Director
From 11.11.2020 onwardsupto 06.11.2024
Mr. N.C. Karmali
(DIN:09103211)
From 20.05.2024 onwards
Mr. Prem Sagar Gupta
(DIN:09329458)
From 06.11.2024 onwards
independent Directors/ Part time Non- Official Directors
Dr. M. V. Natesan
(DIN:09408491)
Independent Director
From 22.11.2021 upto08.11.2024
Mr. Anupam Mallik
(DIN: 09547797)
From 25.03.2022 upto20.03.2025
Mr. Surender Singh
(DIN:11108145)
From 15.05.2025 onwards
*The Company has received declarationsfrom the Independent Directors confirmingthat they meet the criteria of Independenceas prescribed under the Companies Act, 2013and SEBI (LODR) Regulations, 2015 asamended from time to time.
In terms of the provisions of Section 149 of theCompanies Act, 2013 read with theCompanies (Appointment and Qualificationof Directors) Rules, 2014, a Company shall haveat least one-Woman Director on the Board ofthe Company. Further, as per SEBI (LODR)(Amendment) Regulations, 2018, a Companyshall have at least one Independent WomenDirector. Your Company had no Independent
Woman Director on the Board of theCompany since 18.09.2020. The Company hasrequested Ministry of Railways for appointmentof Women Independent Directors in order tocomply with the requirements underRegulation 17 of SEBI (LODR) Regulations 2015and Companies Act, 2013.
The Board of Directors of the Company hasdesignated all the whole-time Directors,Company Secretary, Chief Financial Officer(CFO) as the Key Managerial Personnel (KMP)of the Company; and Chairman & ManagingDirector (CMD) has been designated as CEO.After the close of the year, Executive Director(Finance) has been designated as CFO.
Changes (Appointment/Cessation) in Directors & Key Management Personnel's (KMP) during the yearand till the date of this report is mentioned in Report on Corporate Governance.
Name
Date ofchange
Reasons
Mr. N.C. Karmali(DIN:09103211)
20.05.2024
30.09.2024
Appointment as an AdditionalDirector
Change in Designation from AdditionalDirector to Nominee Director
01.10.2024
Cessation due to Superannuation
Appointment as an Additional
Additional Charge
26.11.2024
Director
Cessation as an Additional Director
06.02.2025
Mr. Prem Sagar Gupta Govt. Nominee Director(DIN:09329458)
06.11.2024
07.11.2024
Cessation due to nominationwithdrawn by appointing authority
09.11.2024
Cessation due to Retirement
Mr. Mritunjay PratapSingh
19.12.2024
21.03.2025
15.05.2025
01.06.2025
Director (Finance)
05.06.2025
Annual evaluation by the Board of its ownperformance and that of its Committees andIndividual Directors-
RVNL being a Government Company isexempted vide Ministry of Corporate Affairs(MCA) General Circular No. F. No. 1/2/2014-CL. V dated 05.06.2015 to comply with theprovisions of Sec 134(3)(e) and Sec 134(3)(p)with respect to Annual evaluation by theBoard of its own performance and that of itsCommittees and Individual Directors andSection 178(2) which requires performanceevaluation of every director by theNomination & Remuneration Committee. Incase of RVNL, the performance evaluationof Directors is done by the Ministry of Railwaysas per their laid down procedure. Further,DPE, through our Administrative Ministry(MOR) has started the exercise ofperformance evaluation/ assessment of non¬official (Independent) Directors on the Boardof the Company.
Retirement of Directors by Rotation
The Companies Act, 2013 provides that theprovisions in respect of retirement of Directorsby rotation will not be applicable toIndependent Directors. In view of this, noIndependent Director is considered to beretiring by rotation; however, all otherdirectors are considered to be retiring byrotation. Accordingly, as per provisions ofsection 152 of Companies Act, 2013, one thirdamong all other directors namely ShriPradeep Gaur, (DIN: 07243986), Chairman &Managing Director, being longest in office,are liable to retire by rotation and beingeligible, offer himself for re-appointment. Thedetails of Director seeking re-appointment atthe ensuing AGM are contained in the Noticeconvening the ensuing AGM of the Company.
Meetings of the Board of Directors and OtherCommittees of the Board and theirComposition
Pursuant to the Companies Act, 2013 andRules framed there under, Seven (7) BoardMeetings were held in the FY 2024-25. Thedetails of the Meetings are in the CorporateGovernance Report forming part of thisreport. Your Company has Audit Committee,CSR Committee, and other Committees ofthe Board in place in compliance toCompliance Act, 2013 and SEBI (LODR)Regulations. The Composition and scope of
the Committees are provided in the reportof Corporate Governance, forming part ofthis report in Annexure-B. Further, there hasbeen no instance where the Board ofDirectors have not accepted therecommendation of Audit Committee.
A Statement regarding Opinion of the Boardwith regard to Integrity, Expertise andExperience (including the Proficiency) of theIndependent Directors appointed during theyear
The Independent directors appointed on theBoard of the Company are eminentpersonalities drawn from fields like Science,Finance, management, industry etc. havingwide experience. Upon induction on theBoard of the Company, the Independentdirectors are familiarized with profile of theCompany, its business, industry scenario,operations, organizational structure,statutory & regulatory responsibilities throughfamiliarization programme. During theFinancial year 2024-25, no IndependentDirector on the board of Rail Vikas NigamLimited (RVNL) has resigned from the post ofIndependent Director. However, the presentIndependent Director has wide experience inthe field of Taxation and has contributedtowards the growth of the Company. In theopinion of the Board, the IndependentDirector fulfils the conditions specified in theListing Regulations and are independent ofthe management.
However, the composition of the Board ofDirectors was not in conformity with theprovisions of the Companies Act, 2013, SEBILODR Regulations and DPE Guidelines onCorporate Governance, due to absence ofrequisite number of Independent Directors(including One-Woman IndependentDirector) on its Board. The Company has beenrequesting Ministry of Railways (MoR),Government of India to appoint requisitenumber of Independent directors (includingone-woman Independent Director) to ensurethe compliance to the provisions of SEBI(LODR) Regulations, 2015 and DPE Guidelineson Corporate Governance. Except theappointment of Independent Directors(including one-woman IndependentDirector), the composition of the Board is incompliance with Regulation 17 of SEBI (LODR)Regulations, 2015.
17. AuditorsStatutory Auditor
The Comptroller & Auditor General of Indiahas appointed M/s. Gandhi Minocha &Co.,Chartered Accountants as Statutory Auditorsof the Company for the year ended 31 March,2025. The Board would like to thank them fortheir valuable support and guidance duringthe audit of accounts under review.
Secretarial Auditor
The Board of Directors has appointed M/sKumar Naresh Sinha & Associates, PracticingCompany Secretary to conduct the SecretarialAudit for financial year 2024-25. The SecretarialAudit Report is annexed and forms part of thisAnnual Report in Annexure E.
18. Reporting of Frauds by Auditors
During the year, neither the Statutory Auditornor the Secretarial Auditor have reported tothe Audit Committee under Section 143(2) ofthe Companies Act, 2013, any instance offraud committed against the Company byits officers or employees.
19. Comments of Comptroller & AuditorGeneral (C&AG) of India
The Comptroller & Auditor General of Indiahas undertaken supplementary audit on theaccounts of the Company for the year ended31 March, 2025 under Section 139(5) of theCompanies Act, 2013. The comments of theC&AG on the Annual Accounts of theCompany for the year ended 31 March, 2025are yet to be received by the company.
20. Details of Significant and Material Orderspassed by the Regulators or Courts orTribunals impacting the Going ConcernStatus and Company's Operations inFuture.
No Significant and Material orders passed bythe Regulators or Courts or Tribunalsimpacting the going concern status andCompany's operations in future during theyear under review
21. Particulars of Employees and RelatedDisclosures
The provisions of Section 134(3)(e) of theCompanies Act, 2013 are not applicable to aGovernment Company. Similarly, Section 197of the Companies Act, 2013 shall not apply toa Government Company. Consequently,
there is no requirement of disclosure of the ratioof the remuneration of each Director to themedian employee's remuneration and othersuch details, including the statement showingthe names and other particulars of everyemployee of the Company, who, if employedthroughout/part of the financial year, was inreceipt of remuneration in excess of the limitsset out in the Rules.
22. Material Changes and Commitmentsaffecting Financial position between theend of the Financial Year and Date ofReport
There are no material changes andcommitments affecting financial position ofthe Company which occurred between01.04.2024 to 31.03.2025 and date of signingof this Report.
23. Cost Records
The Board of Directors has appointed M/s.R. M. Bansal & Co., Cost Accountants toconduct the Cost Audit for financial year2024-25.
24. Difference in amount of the Valuation
There was no such instance of eithersettlement or loan from Bank or FinancialInstitution during the year under review.
25. General
Your Directors state that no disclosure orreporting is required in respect of thefollowing matters as there were notransactions on these matters during the yearunder review:
Details relating to deposits covered underChapter V of the Companies Act 2013.
Issue of equity shares with differential rightsas to dividend, voting or otherwise.
There has been no change in the natureof business of the Company.
26. Corporate Insolvency ResolutionProcess initiated under the Insolvencyand Bankruptcy Code, 2016
The Company has no information to discloseunder above.
27. Failure to implement any CorporateAction
The Company has implemented allCorporate Actions successfully withinprescribed timelines. Therefore, the Companyhas nothing to report.
Your Directors also take this opportunity togratefully acknowledge the co-operation,guidance, and support in effectivemanagement of company's affairs andresources provided by Government of India,in particular Ministry of Railways (MoR), Ministryof Finance, Department of Public Enterprises,various banks, Asian Development Bank, theZonal Railways, IRFC and our equity partnersin Joint Venture/SPVs for their continuedinterest and support to the Company. YourDirectors would like to express their thanksfor the devotion, commitment anddedication of each and every employee ofthe Company due to which your Companycould face the new challenges andopportunities and create a niche for itself asa major provider of rail infrastructure in thecountry. Your Directors also acknowledge the
support and guidance received from officialsof Comptroller & Auditor General of India,Statutory Auditors, Cost Auditors andSecretarial Auditors for their suggestions. Lastbut not the least, the Directors would like toexpress their deep appreciation and gratitudetowards all their predecessors who have beenassociated with RVNL, for their valuablecontribution to the growth and developmentof the Company in attainment of theCompany's aim and goals in all the spheres.
For and on behalf of Board of Directors
(Pradeep Gaur)Chairman & Managing DirectorDIN:07243986